Kenneth N. Butz, Jr. Elementary School

Work Ongoing

• Submittal processing • InWall Electrical Rough-in • In Stone Electrical Rough-in at Gym • Coordination of Porous Paving at new parking area • Coordination with district on construction related items that may affect traffic • Coordination of EC switchgear panel installation • Coordination and installation of MEP in-wall rough ins • Interior Classroom CMU walls • Sheathing parapet walls • Steel framing of Gym and Storage area • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping • Placement of roof curbs for RTU units and exhaust fans • Procurement of roofing materials • Procurement of Brick Work Ongoing

Hauling Fill Off Site

Infiltration Testing at Basin #2

Made with FlippingBook - Online Brochure Maker