Whitehall Municipal Campus Improvements Whitehall Township
Construction Manager
WHITEHALL MUNICIPAL CAMPUS Whitehall Township
DEI Project No.719001 Monthly Progress Report No.18 November & December 2021
Work Completed
Phase 3: Renovation of Existing Municipal Building, Construction of Alternate Elevator, Construction of Solar Canopy, Completion of Exterior Improvements, Final Finishes Police Addition • Start: April 2021 • Completion of Phase: December 2021 Phase 3: Existing Municipal Building Renovation, Completion of Police Addition Finishes • Complete and turned over to the Township for use on 11/01/21 WORK COMPLETED - Existing Building Renovation Phase 3
• Maintaining Erosion and Sediment controls • Completing punch list items WORK IN PROGRESS - Site
• Completed and turned over to the Police for use on 12/21/21, the date of project substantial completion • Completing punch list items • Owner training • Installation of new furniture purchased by the Township Police Addition Phase 2
Front Facade
Community Transaction Room
November & December 2021
Work In progress
• Added Scope-Board and Caucus Room Renovations • Completion and inspection of alternate elevator Existing Building Renovation Phase 3 -Remaining Work
• Public Meeting Room finishes • Police move • Installation of exterior Township signage • Exterior painting Work In Progress
Monumental Stairs
Elevator Addition
PSA Office
Police Roll Call Room
Detectives Offices
November & December 2021
Renders
November & December 2021
Site Plan
November & December 2021
Floor Plan
First Floor Plan
Second Floor Plan
November & December 2021
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Municipal Building Phase 3 Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion
M-A M J-F Contract Phases
Current Phase and Schedule Status
M-J J-A
J-F M-A
S-O N-D
Renovate Existing Municipal Building Phase 3 ‐ Elevator Construction ‐ Interior Finishes Phase 2 ‐ Final Finishes Added Scope ‐ Board and Caucus Rooms Site Work Substantial Completion / Final Completion
Issues Resolved
Contractor COVID ‐ 19 Protocols provided and implemented onsite
Paid to Date
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
Contract Amount
$ $ $ $ $ $
$ $ $ $ $ $ $ $
3,958,464 13,771,429 9,680,000 1,081,000 1,779,500 1,139,000 91,929
Total Total Soft Costs: Current Remaining Project Contingency
908,850
Report Submission Date:
November ‐ December 2021
Report Author:
Kim LaBrake
2021
2022
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
Each scheduled task extended 6 weeks
100% 100% 100% 100% 100% 50% 100% 99%
Board Room & Caucus room finishes to be completed
Substantial Completeion date 12/21/21
s FP1 & B1 2020 ‐ 2021
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O
N-D
% Complete
100% 100% 100% 100%
Elevator Addition Floor finishes
Board Room & Caucus room finishes to be completed Floor Finishes, Touch up Painting
99%
100%
50%
Issues in Progress
Coordinate furniture delivery and Police move
Original Material Allowance
Executed Change Orders 471,922 $
Remaining Material Allowance 43,367 $ 4,938 $ 17,725 $ 28,575 $ ‐ $ 94,606 $
e (with 5% retained)
10,062,814 1,029,727 1,784,722 1,091,233
$ $ $ $ $ $
28,800 61,380 164,850 17,375
$ $ $ $ $
24,013 285,931 53,060 854,568 19,643
6,000
111,572
14,080,068
278,405
Printed 1/5/2022 1 of 1
Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President
Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member
Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor