Whitehall Township Municipal Campus

WORK IN PROGRESS - Site • Maintaining Erosion and Sediment controls • Installation of light bases and poles

• Final MEP ceiling and wall finishes cell block and evidence pro- cessing area • Installation of cameras and card access hardware • Installation of interior metal doors • Programming of ATC controls • Architectural and MEP Punch lists for the cell block, evidence processing area, and second floor Police Addition Phase 2

Cell Block Area

Alternate Elevator

June 2021

Made with FlippingBook - Online catalogs