Whitehall Township Municipal Campus
Animated publication
Whitehall Municipal Campus Improvements Whitehall Township
Construction Manager
WHITEHALL MUNICIPAL CAMPUS Whitehall Township
DEI Project No.719001 Monthly Progress Report No.13 June 2021
Work Completed
Phase 3: Existing Municipal Building Renovation, Completion of Police Addition Finishes
• Phase 3: Renovation of Existing Municipal Building, Construction of Alternate Elevator, Construction of Solar Canopy, Completion of Exterior Improvements, Final Finishes Police Addition • Start: April 2021 • Completion of Phase: December 2021 • Installation of jail cell equipment and doors • Installation of high-density storage • Installation of narcotics cabinet and gun lockers • Finish paint in cell block and evidence processing area • Installation of MEP finishes in cell block and evidence processing area • Final cleaning Police Addition Second floor WORK COMPLETED - Police Addition Phase 2
WORK IN PROGRESS - Site • Maintaining Erosion and Sediment controls • Installation of light bases and poles
• Final MEP ceiling and wall finishes cell block and evidence pro- cessing area • Installation of cameras and card access hardware • Installation of interior metal doors • Programming of ATC controls • Architectural and MEP Punch lists for the cell block, evidence processing area, and second floor Police Addition Phase 2
Cell Block Area
Alternate Elevator
June 2021
Work In progress
Existing Building Renovation Phase 3
• Installation of exterior metal framing, sheathing, and brick veneer • Installation of interior metal framing, insulation, and drywall • Maintaining of temporary power and lighting • Overhead rough-in of lighting, power, and security systems • Installation of floor boxes for power and data distribution • Installation of new heating and cooling equipment • Overhead mechanical rough in including insulation of heating and cooling piping • Installation of domestic and rain water piping • Coordination of MEP rough-in for new elevator addition • Coordination of contractor lay down areas for materials and equipment
Municipal Building Exterior Facade
Evidence Processing
Municipal Renovations
New Condensing Units on Existing Roof
June 2021
Renders
June 2021
Site Plan
June 2021
Floor Plan
First Floor Plan
Second Floor Plan
June 2021
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Municipal Building Phase 3 Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion
Contract Phases M-A M J-F
Current Phase and Schedule Status
J-F M-A M-J J-A S-O N-D
Renovate Existing Municipal Building Phase 3 ‐ Environmental remediation ‐ Interior Demolition
‐ Elevator Construction ‐ Exterior wall panels ‐ Interior framing ‐ Gypsum Board Installation
‐ MEP Wall Rough ‐ in ‐ MEP Ceiling Rough ‐ in Site Work
Issues Resolved
Contractor COVID ‐ 19 Protocols provided and implemented onsite Additional existing material environmental testing
Paid to Date
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
Contract Amount
$ $ $ $ $ $ $ $
9,680,000 1,081,000 1,779,500 1,139,000 13,771,429 3,958,464 91,929
$ $ $ $ $ $
Total Total Soft Costs: Current Remaining Project Contingency
908,850
Report Submission Date:
June 2021
Report Author:
Kim LaBrake
2021
2022
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
100% 100% 100% 100%
Each scheduled task extended 6 weeks
Includes Abatement and interior wall demolition
45%
0%
75% 0%
s FP1 & B1 2020 ‐ 2021
Status Comments
M-J J-A
S-O N-D
M-J
J-A S-O N-D
J-F M-A
% Complete
45%
100% 100%
60% 75% 60% 30% 90% 10% 40%
Issues in Progress
Existing Township Building Concrete Slab Vapor Barrier Confirmation Doors and hardware delivery
Executed Change Orders
Original Material Allowance
Remaining Material Allowance 96,579 $ 8,792 $ 33,791 $ 29,511 $ ‐ $ 168,673 $
e (with 5% retained)
$ $ $ $ $ $
43,421
$ $ $ $ $ $
278,405 17,375 6,000 61,380 28,800 164,850
1,046,815 1,394,852 993,224 7,965,770
‐ ‐ ‐
93,072
44,564 1,143
11,493,732
Printed 7/8/2021 1 of 1
Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President
Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member
Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor
Made with FlippingBook - Online catalogs