Whitehall Township Municipal Campus

Animated publication

Whitehall Municipal Campus Improvements Whitehall Township

Construction Manager

WHITEHALL MUNICIPAL CAMPUS Whitehall Township

DEI Project No.719001 Monthly Progress Report No.13 June 2021

Work Completed

Phase 3: Existing Municipal Building Renovation, Completion of Police Addition Finishes

• Phase 3: Renovation of Existing Municipal Building, Construction of Alternate Elevator, Construction of Solar Canopy, Completion of Exterior Improvements, Final Finishes Police Addition • Start: April 2021 • Completion of Phase: December 2021 • Installation of jail cell equipment and doors • Installation of high-density storage • Installation of narcotics cabinet and gun lockers • Finish paint in cell block and evidence processing area • Installation of MEP finishes in cell block and evidence processing area • Final cleaning Police Addition Second floor WORK COMPLETED - Police Addition Phase 2

WORK IN PROGRESS - Site • Maintaining Erosion and Sediment controls • Installation of light bases and poles

• Final MEP ceiling and wall finishes cell block and evidence pro- cessing area • Installation of cameras and card access hardware • Installation of interior metal doors • Programming of ATC controls • Architectural and MEP Punch lists for the cell block, evidence processing area, and second floor Police Addition Phase 2

Cell Block Area

Alternate Elevator

June 2021

Work In progress

Existing Building Renovation Phase 3

• Installation of exterior metal framing, sheathing, and brick veneer • Installation of interior metal framing, insulation, and drywall • Maintaining of temporary power and lighting • Overhead rough-in of lighting, power, and security systems • Installation of floor boxes for power and data distribution • Installation of new heating and cooling equipment • Overhead mechanical rough in including insulation of heating and cooling piping • Installation of domestic and rain water piping • Coordination of MEP rough-in for new elevator addition • Coordination of contractor lay down areas for materials and equipment

Municipal Building Exterior Facade

Evidence Processing

Municipal Renovations

New Condensing Units on Existing Roof

June 2021

Renders

June 2021

Site Plan

June 2021

Floor Plan

First Floor Plan

Second Floor Plan

June 2021

Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001

2020

Overall Project Schedule Status

J-F

M-A M

J-F M-A M-J J-A S-O N-D

Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Municipal Building Phase 3 Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion

Contract Phases M-A M J-F

Current Phase and Schedule Status

J-F M-A M-J J-A S-O N-D

Renovate Existing Municipal Building Phase 3 ‐ Environmental remediation ‐ Interior Demolition

‐ Elevator Construction ‐ Exterior wall panels ‐ Interior framing ‐ Gypsum Board Installation

‐ MEP Wall Rough ‐ in ‐ MEP Ceiling Rough ‐ in Site Work

Issues Resolved

Contractor COVID ‐ 19 Protocols provided and implemented onsite Additional existing material environmental testing

Paid to Date

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]

Contract Amount

$ $ $ $ $ $ $ $

9,680,000 1,081,000 1,779,500 1,139,000 13,771,429 3,958,464 91,929

$ $ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency

908,850

Report Submission Date:

June 2021

Report Author:

Kim LaBrake

2021

2022

Status Comments

M-J J-A

S-O N-D

J-F M-A M-J

J-A S-O N-D

% Complete

100% 100% 100% 100%

Each scheduled task extended 6 weeks

Includes Abatement and interior wall demolition

45%

0%

75% 0%

s FP1 & B1 2020 ‐ 2021

Status Comments

M-J J-A

S-O N-D

M-J

J-A S-O N-D

J-F M-A

% Complete

45%

100% 100%

60% 75% 60% 30% 90% 10% 40%

Issues in Progress

Existing Township Building Concrete Slab Vapor Barrier Confirmation Doors and hardware delivery

Executed Change Orders

Original Material Allowance

Remaining Material Allowance 96,579 $ 8,792 $ 33,791 $ 29,511 $ ‐ $ 168,673 $

e (with 5% retained)

$ $ $ $ $ $

43,421

$ $ $ $ $ $

278,405 17,375 6,000 61,380 28,800 164,850

1,046,815 1,394,852 993,224 7,965,770

‐ ‐ ‐

93,072

44,564 1,143

11,493,732

Printed 7/8/2021 1 of 1

Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President

Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member

Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor