Whitehall Municipal Campus Improvements Whitehall Township

Construction Manager

WHITEHALL MUNICIPAL CAMPUS Whitehall Township

DEI Project No.719001 Monthly Progress Report No.12 May 2021

Work Completed

Phase 3: Existing Municipal Building Renovation, Completion of Police Addition Finishes

• Phase 3: Renovation of Existing Municipal Building, Construction of Alternate Elevator, Construction of Solar Canopy, Completion of Exterior Improvements, Final Finishes Police Addition • Start: April 2021 • Completion of Phase: December 2021 • Installation of acoustical and drywall ceilings second floor, cell block, and evidence processing/storage area • Installation of casework in cell block area and evidence processing area • Installation of ceramic tile, carpet, VCT flooring and cove base second floor WORK COMPLETED - Police Addition Phase 2

• Installation of bathroom accessories Second floor Police Addition • Installation of window shades Second floor • Installation of roof coping • Installation of exterior metal panels and joint sealants WORK COMPLETED - Police Addition Phase 2 (Cont.)

• Final grading and seeding of north side of building Work Completed - Site

Existing Municipal Building Selective Demolition

Alternate Elevator Foundations

May 2021

Work In progress

• Maintaining Erosion and Sediment controls • Installation of light bases and poles • Waterproofing and backfilling of elevator addition WORK IN PROGRESS - Site • Finish paint cell block area and evidence processing area • Final MEP ceiling and wall finishes Work in progress - Police Addition Phase 2

Second Floor Commons Area Ceramic Tile

Second Floor Corridor

Solar Canopy

Detective’s Second Floor Work Area

• Demolition of existing ceilings, floors, interior, and exterior walls • Demolition of existing lighting, fire alarm and security systems • Demolition of existing air handlers and roof top equipment • Overhead rough-in of electrical systems • Plumbing rough in for new single toilet rooms • Coordination of MEP rough-in for new elevator addition • Relocation of existing rain leaders • Layout of walls for installation of interior metal framing • New ceramic flooring installed in existing single toilet rooms • Installation of solar canopy equipment including panels and inverters • Coordination of contractor lay down areas for materials and equipment • Completion of abatement of floor mastic in existing municipal building Work in progress - Existing Building Renovation Phase 3

May 2021

Renders

May 2021

Site Plan

May 2021

Floor Plan

First Floor Plan

Second Floor Plan

May 2021

Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001

2020

Overall Project Schedule Status

J-F

M-A M

J-F M-A M-J J-A S-O N-D

Construct New Public Works Facility Construct Police Addition Phase 1 - Foundations & Building Pad Construct Police Addition Phase 2 - Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Municipal Building Phase 3 Police Addition Phase 2 - Final Finishes Site Work Substantial Completion / Final Completion

Contract Phases M-A M J-F

Current Phase and Schedule Status

J-F M-A M-J J-A S-O N-D

Township Office move Renovate Existing Municipal Building Phase 3 - Environmental remediation - Interior Demolition - Elevator Construction Site Work

Issues Resolved

Contractor COVID-19 Protocols provided and implemented onsite

Paid to Date

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]

Contract Amount

$ $ $ $ $ $ $ $

3,958,464 13,771,429 1,139,000 1,779,500 1,081,000 9,680,000 91,929

$ $ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency

908,850

Report Submission Date:

May 2021

Report Author:

Kim LaBrake

2021

2022

Status Comments

M-J J-A

S-O N-D

J-F M-A M-J

J-A S-O N-D

% Complete

100% 100% 100% 100%

Each scheduled task extended 6 weeks

Includes Abatement and interior wall demolition

20%

0%

75% 0%

s FP1 & B1 2020 -2021

Status Comments

M-J J-A

S-O N-D

M-J

J-A S-O N-D

J-F M-A

% Complete

100%

90% 25% 75% 95% 20%

Issues in Progress

Existing Township Building Concrete Slab Vapor Barrier Confirmation Doors and hardware delivery

Additional existing material environmental testing

Executed Change Orders

Original Material Allowance

Remaining Material Allowance 97,856 $ 8,792 $ 52,738 $ 29,511 $ - $ 188,896 $

e (with 5% retained)

7,810,265

$ $ $ $ $ $

43,421

$ $ $ $ $ $

164,850 28,800 61,380 17,375 6,000 278,405

978,521

- - -

1,042,731 1,345,704

93,072

1,143

11,270,293

44,564

Printed 6/8/2021 1 of 1

Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President

Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member

Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor