Whitehall Municipal Campus - October & November 2020
Whitehall Municipal Campus Improvements Whitehall Township
Construction Manager
WHITEHALL MUNICIPAL CAMPUS Whitehall Township
DEI Project No.719001 Monthly Progress Report No.06 October & November 2020
Work Completed
• Phase 2: Construction of Public Works Storage Building, Construction of Police Addition, Demolition of Existing Garages, Prepare subgrade/grade for Surrounding Parking Lots and Roads • Start: August 2020 • Completion of Phase: April 2021 Phase 2: Public Works Facility, Building Area B2.1-B2.18
• Placement of Temporary Office Trailers and Storage Containers • Temporary partitions previously installed in existing building are being maintained to keep building weathertight • Completed Structural Wood Decking in Lobby • Completed Installation of Roof Drains in Police Addition WORK COMPLETED - Police Addition Phase 2
Maintenance Storage Building
• Install finishes in Shop Area under mezzanine • Final painting of CMU walls, Metal Stairs and Safety Rails Work Completed - Maintenance Storage
• Install Lightning Protection System • Install Overhead Coiling Garage Doors
• Paving of Areas around Fuel Station and Maintenance Building • Maintaining Erosion & Sediment Controls Work IN progress - Site
Second Floor Interior Metal Framing
• Coordination of Fire Alarm System • Installation of Lighting Controls • Final Cleaning Work IN progress - Maintenance Storage
October & November 2020
Work In progress
WORK IN PROGRESS - Police Addition Phase 2
• Continue installation of Slab on Grade First Floor Police Addition • Installation of Exterior Brick Veneer • Interior MasonryWall Construction Police Addition including MEP Rough In • Installation of Roof above Structural Wood Decking in Lobby • Police Addition Roof including Roof Top and Exhaust Fan Curbs • Exterior Sheathing and Spray Applied Vapor Barrier • Second Floor Mechanical Ductwork including Insulation and Coordination of Interior Wall Openings • Second Floor Electrical Rough-in including Low Voltage Pathways • Preparation of Existing Township Garage for Demolition • Installation of Interior Metal Framing, Window Framing and Door Frames
Police Addition Roof
Overhead Electrical Rough
First Floor Masonry Walls
Second Floor Duct Work
October & November 2020
Renders
October & November 2020
Site Plan
October & November 2020
Floor Plan
First Floor Plan
Second Floor Plan
October & November 2020
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes
Demolition of Existing Garage Buildings Renovate Existing Township Building Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion
Contract Phases M-A M J-F
Current Phase and Schedule Status
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Police Addition Phase 2 ‐ Structural steel erection ‐ 1st Floor MEP Non‐Bearing wall rough‐in (above slab) ‐ Exterior Cold Form Framing ‐ 2nd Floor Interior Cold Form Framing
‐ 1st Floor Concrete Slabs ‐ 1st Floor MEP Rough‐In ‐ 2nd Floor MEP Rough‐In
‐ 2nd Floor Roof ‐ 1st Floor Roof
‐ Lobby Roof Township Office move Demolition of Existing Garage Buildings Site Work
Issues Resolved Contractor COVID‐19 Protocols provided and implemented onsite
$ $ $ $ $ $ Paid to Date
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
1,139,000 $ 91,929 $ 1,779,500 $ 9,680,000 $ Contract Amount 13,771,429 $ 3,958,464 $ 908,850 $ 1,081,000 $
Total Total Soft Costs: Current Remaining Project Contingency
Report Submission Date:
Oct./Nov. 2020
Report Author:
Kim LaBrake
2021
2022
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
99%
Each schedule task extended 6 weeks
100%
30% 50%
2%
35% 0% 0%
s FP1 & B1 2020 ‐2021
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
90% Mezzanine stair and floor slab installation
40%
95% Misc. steel at Cells to be installed in coordination with bearing walls 50% 95%
90% 90% 15% 40% 85% 80% 50%
4%
30%
30% Banks graded at rear of Maintenance Building
Issues in Progress Existing Township Building Concrete Slab Vapor Barrier Confirmation Review of Air/Vapor Barrier installation
‐ $ 1,143 $ ‐ $ 21,622 $ 20,480 $ ‐ $ Executed Change Orders
17,375 $ 6,000 $ 278,405 $ 61,380 $ 164,850 $ 28,800 $ Original Material Allowance
Remaining Material Allowance 147,947 $ 28,800 $ 61,380 $ 17,375 $ ‐ $ 255,502 $
e (with 10% retained)
589,830 66,494 484,578 4,642,602 443,835 6,227,338
Printed 12/3/2020
Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President
Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member
Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor