Whitehall Municipal Campus Improvements
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Municipal Building Phase 3 Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion
Contract Phases M-A M J-F
Current Phase and Schedule Status
J-F M-A M-J J-A S-O N-D
Renovate Existing Municipal Building Phase 3 ‐ Elevator Construction
‐ Exterior wall panels/Brick ‐ Gypsum Board Installation ‐ MEP Ceiling Rough ‐ in ‐ Interior Finishes Added Scope ‐ Demolition Site Work
Issues Resolved
Contractor COVID ‐ 19 Protocols provided and implemented onsite
Additional existing material environmental testing
Township added scope request
Existing Township Building Concrete Slab Vapor Barrier Confirmation
Paid to Date
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
Contract Amount
$ $ $ $ $ $ $ $
9,680,000 1,081,000 1,779,500 1,139,000 13,771,429 3,958,464 91,929
$ $ $ $ $ $
Total Total Soft Costs: Current Remaining Project Contingency
908,850