Work In progress

• Maintaining Erosion and Sediment controls • Installation of sidewalks Work In Progress - Site

WORK IN PROGRESS - Police Addition Phase 2

• Installation of acoustical and drywall ceilings • Interior caulking of door and window frames Second floor • Finish paint First and Second floor • Start-up of fire alarm, ATC and generator systems • Coordination of new data and network startup and testing • First and Second floor mechanical final ceiling connections • Integration of existing fire protection system to Police Addition • Installation of the elevator • Installation of overhead coiling doors • Above ceiling electrical and mechanical inspections

Data Cabling

Boilers