Overall Project Schedule Status

J-F

M-A M

J-F M-A M-J J-A S-O N-D

Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes

Demolition of Existing Garage Buildings Renovate Existing Township Building Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion

Contract Phases M-A M J-F

Current Phase and Schedule Status

J-F M-A M-J J-A S-O N-D

Police Addition Phase 2

‐ Exterior Masonry ‐ Police Addition ‐ 1st Floor MEP Rough ‐ In ‐ 2nd Floor MEP Rough ‐ In

‐ 2nd Floor Roof ‐ 1st Floor Roof ‐ Lobby Roof ‐ Exterior Metal Panel ‐ Windows ‐ Police Addition

Township Office move Site Work

Contractor COVID ‐ 19 Protocols provided and implemented onsite Issues Resolved

Paid to Date

Contract Amount

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]

$ $ $ $ $ $ $ $

1,139,000 1,779,500 1,081,000 9,680,000 13,771,429 3,958,464 91,929

$ $ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency