Whitehall Municipal Campus Improvements
Work Completed
• Phase 2: Construction of Public Works Storage Building, Construction of Police Addition, Demolition of Existing Garages, Prepare subgrade/grade for Surrounding Parking Lots and Roads • Start: August 2020 • Completion of Phase: April 2021 Phase 2: Public Works Facility, Building Area B2.1-B2.18
WORK COMPLETED - Police Addition Phase 2
• Completed demolition of existing Township garages • Temporary partitions previously installed in existing building are being maintained to keep building weathertight • Completed slab on grade for first floor Police Addition • Completed roof on Police Addition • Completed paving at Fuel Station and Maintenance Building
Demolition of Existing Township Garages