Whitehall Municipal Campus Improvements
Animated publication
Whitehall Municipal Campus Improvements Whitehall Township
Construction Manager
WHITEHALL MUNICIPAL CAMPUS Whitehall Township
DEI Project No.719001 Monthly Progress Report No.07 December 2020
Work Completed
• Phase 2: Construction of Public Works Storage Building, Construction of Police Addition, Demolition of Existing Garages, Prepare subgrade/grade for Surrounding Parking Lots and Roads • Start: August 2020 • Completion of Phase: April 2021 Phase 2: Public Works Facility, Building Area B2.1-B2.18
WORK COMPLETED - Police Addition Phase 2
• Completed demolition of existing Township garages • Temporary partitions previously installed in existing building are being maintained to keep building weathertight • Completed slab on grade for first floor Police Addition • Completed roof on Police Addition • Completed paving at Fuel Station and Maintenance Building
Demolition of Existing Township Garages
Work Completed - Maintenance Storage
• Substantial Completion obtained on December 3, 2020.
• Maintaining Erosion & Sediment controls • Preparing new parking lot subgrade Work IN progress - Site
Installation of Main Electric Room Switchgear
• Architect’s Punchlist Work IN progress - Maintenance Storage
December 2020
Work In progress
WORK IN PROGRESS - Police Addition Phase 2
• Exterior sheathing and spray applied vapor barrier • Installation of second floor exterior windows and aluminum storefront • Installation of exterior brick veneer • Interior masonry wall construction including MEP rough-in • First and second floor mechanical ductwork including insulation and coordina- tion of interior wall openings • First and second floor electrical rough-in including low voltage pathways • Installation of main electrical room • Electrical rough-in for elevator • Installation of interior metal framing, window framing and door frames • Installation of wood blocking and sound insulation • MEP in-wall inspection of interior metal framing • Installation of drywall on second floor • Installation and testing of domestic water lines including insulation of piping first and second floor • Installation of rear and monumental stairs • Painting of First floor CMU walls • Maintaining temporary heat throughout Police Addition
Deputy Chief’s Office with Aluminum Storefront
Preparation of New Parking Area
First Floor Bathroom Plumbing Rough-In
Second Floor Exterior Windows
December 2020
Renders
December 2020
Site Plan
December 2020
Floor Plan
First Floor Plan
Second Floor Plan
December 2020
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes
Demolition of Existing Garage Buildings Renovate Existing Township Building Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion
Contract Phases
Current Phase and Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Police Addition Phase 2 ‐ Structural steel erection
‐ 1st Floor MEP Non ‐ Bearing wall rough ‐ in (above slab) ‐ Exterior Cold Form Framing ‐ 2nd Floor Interior Cold Form Framing
‐ 1st Floor Concrete Slabs ‐ 1st Floor MEP Rough ‐ In ‐ 2nd Floor MEP Rough ‐ In
‐ 2nd Floor Roof ‐ 1st Floor Roof ‐ Lobby Roof
Township Office move Demolition of Existing Garage Buildings Site Work
Issues Resolved Contractor COVID ‐ 19 Protocols provided and implemented onsite
Paid to Date
Contract Amount
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
$ $ $ $ $ $
$ $ $ $ $ $ $ $
1,139,000 1,779,500 1,081,000 9,680,000 13,771,429 3,958,464 91,929
Total Total Soft Costs: Current Remaining Project Contingency
908,850
Report Submission Date:
December 2020
Report Author:
Kim LaBrake
2021
2022
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
100% 100%
Each schedule task extended 6 weeks
60%
100%
2%
35% 0% 0%
s FP1 & B1 2020 ‐ 2021
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
100%
60%
100% 60% 99% 100% 95%
75% 90% 95% 95% 40%
4%
100%
Issues in Progress Existing Township Building Concrete Slab Vapor Barrier Confirmation Remediation and reapplication of exterior Air/Vapor Barrier installation 35%
Executed Change Orders
Original Material Allowance
Remaining Material Allowance 117,392 $ 12,282 $ 61,380 $ 29,511 $ ‐ $ 220,565 $
e (with 10% retained)
5,348,472
$ $ $ $ $ $
22,586
$ $ $ $ $ $
17,375 6,000 278,405 61,380 164,850 28,800
603,653 66,494 605,790 519,848
‐ ‐ ‐
1,143
7,144,256
23,729
Printed 1/6/2021 1 of 1
Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President
Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member
Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor
Made with FlippingBook Publishing Software