Whitehall Municipal Campus Improvements - April 2021
Second Floor Commons Area Ceramic Tile
Second Floor Work Area
Existing Building Renovation Phase 3
• Moving of Township furniture, filing cabinets and computer equipment to Police Addition. • Preparation, abatement, and testing of floor tiles in existing building. • Coordination of demolition for existing life safety systems. • Coordination of demolition schedule among contractors. • Contractor layout and ordering of materials for next phase of construction.