Whitehall Municipal Campus Improvements - April 2021
Animated publication
Whitehall Municipal Campus Improvements Whitehall Township
Construction Manager
WHITEHALL MUNICIPAL CAMPUS Whitehall Township
DEI Project No.719001 Monthly Progress Report No.11 April 2021
Work Completed
Phase 3: Existing Municipal Building Renovation, Completion of Police Addition Finishes
• Phase 3: Renovation of Existing Municipal Building, Construction of Alternate Elevator, Construction of Solar Canopy, Completion of Exterior Improvements, Final Finishes Police Addition • Start: August 2021 • Completion of Phase: December 2021 • Temporary occupancy was approved on April 14th, 2021. • Temporary move of Township employees to Police addition. WORK COMPLETED - Police Addition Phase 2
• Installation of solar canopy structure. • Paving of new Police parking area. Work Completed - Site
Police Addition
Alternate Elevator Foundation
Men’s Police Lockers
April 2021
Work In progress
• Maintaining Erosion and Sediment controls. • Installation of sidewalks. • Final grading and seeding on northside of building. • Installation of light bases. • Excavation of elevator addition. Work In Progress - Site
• Installation of acoustical and drywall ceilings second floor, cell block, and evidence processing/storage area. • Finish painting on second floor. • Installation of ceramic tile second floor bathrooms, locker rooms, and monumental stair commons area. •Installation of card access and camera system. Police Addition Phase 2
Environmental Remediation
Solar Canopy
Second Floor Commons Area Ceramic Tile
Second Floor Work Area
Existing Building Renovation Phase 3
• Moving of Township furniture, filing cabinets and computer equipment to Police Addition. • Preparation, abatement, and testing of floor tiles in existing building. • Coordination of demolition for existing life safety systems. • Coordination of demolition schedule among contractors. • Contractor layout and ordering of materials for next phase of construction.
April 2021
Renders
April 2021
Site Plan
April 2021
Floor Plan
First Floor Plan
Second Floor Plan
April 2021
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Municipal Building Phase 3 Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion
Contract Phases M-A M J-F
Current Phase and Schedule Status
J-F M-A M-J J-A S-O N-D
Police Addition Phase 2 ‐ Except Finishes Township Office move Renovate Existing Municipal Building Phase 3 ‐ Environmental remediation ‐ Interior Demolition ‐ Elevator Construction Site Work
Contractor COVID ‐ 19 Protocols provided and implemented onsite Issues Resolved
Paid to Date
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
Contract Amount
$ $ $ $ $ $ $ $
13,771,429 3,958,464 1,139,000 1,779,500 1,081,000 9,680,000 91,929
$ $ $ $ $ $
Total Total Soft Costs: Current Remaining Project Contingency
908,850
Report Submission Date:
April 2021
Report Author:
Kim LaBrake
2021
2022
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
100% 100% 100% 100%
Each scheduled task extended 6 weeks
10% 65% 0% 0%
s FP1 & B1 2020 ‐ 2021
Status Comments
M-J
M-J J-A
S-O N-D
J-A S-O N-D
J-F M-A
% Complete
100%
50% Temporary move to Police Addition
2% 15% 90% 65% 10%
Final grading & seeding north side of building
Issues in Progress
Existing Township Building Concrete Slab Vapor Barrier Confirmation Doors and hardware delivery
Executed Change Orders
Original Material Allowance
Remaining Material Allowance 97,856 $ 8,792 $ 52,738 $ 29,511 $ ‐ $ 188,896 $
e (with 5% retained)
$ $ $ $ $ $
43,421
$ $ $ $ $ $
164,850 28,800 61,380 17,375 6,000 278,405
7,939,026 1,006,253 1,357,720 1,084,841
‐ ‐ ‐
66,494
44,564 1,143
11,454,334
Printed 5/10/2021 1 of 1
Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President
Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member
Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor
Made with FlippingBook - professional solution for displaying marketing and sales documents online