Whitehall Municipal Campus Improvements

Animated publication

Whitehall Municipal Campus Improvements Whitehall Township

Construction Manager

WHITEHALL MUNICIPAL CAMPUS Whitehall Township

DEI Project No.719001 Monthly Progress Report No.05 September 2020

Work Completed

• Phase 2: Construction of Public Works Storage Building, Construction of Police Addition, Demolition of Existing Garages, Prepare subgrade/grade for Surrounding Parking Lots and Roads • Start: August 2020 • Completion of Phase: April 2021 Phase 2: Public Works Facility, Building Area B2.1-B2.18

WORK COMPLETED - Police Addition Phase 2

• Completed CMU bearing walls for Police Addition Building Area 2 • Completed Second Floor Concrete Slabs • Temporary partitions previously installed in existing building are being maintained to keep building weathertight

Police Addition Exterior Framing

• Installed metal stairs to mezzanine • Installed lights and fire alarm devices • Installed cold form framing • Installed sub framing for ceiling construction under mezzanine • Grade banks behind Public Works Storage Building Maintenance Storage

• Prepare new parking areas and loop road for paving WORk IN progress - Site

First Floor Vapor Barrier in Police Addition

• First Floor Concrete Slab Pours • MEP Rough-In of MasonryWalls • Install Door Frames Police Addition WORk IN progress - Site

September 2020

Work In progress

WORK IN PROGRESS - Police Addition Phase 2 continued

• Installation of Structural Wood Deck in Lobby • Installation of Roof Drain Piping Second Floor • Connection of Roof Drain Piping First Floor • Installation of temporary lighting

• Install Steel Lentils in MasonryWalls for Duct Openings • Installation of Hangers for Mechanical Piping Second Floor • Installation of Hangers for HVAC Ductwork Second Floor • Installation of Plumbing Fixture Carriers Second Floor • Construction of Exterior Masonry Mock-up Panel for review and approval • Coordination of New SECTV Cable and Data Service

Structural Wood Decking In Entrance Lobby

Public Works Mezzanine Stair

Cell Block Area

Graded Banks at Maintenance Building

September 2020

Renders

September 2020

Site PLan

September 2020

Floor PLan

First Floor Plan

Second Floor Plan

September 2020

Whitehall Township Project Name:  Municipal Campus Improvements Project Number:  719001

2020

Overall Project Schedule Status

J-F

M-A M

J-F M-A M-J J-A S-O N-D

Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Township Building  Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion Construct New Public Works Facility Police Addition Phase 1 Police Addition Phase 2                    ‐ Structural steel erection Current Phase and Schedule Status                   ‐ Exterior Cold Form Framing                   ‐ 2nd Floor Concrete Slabs                   ‐ 1st Floor Concrete Slabs Township Office move  Demolition of Existing Garage Buildings Site Work                   ‐ MEP Bearing wall rough‐in (above slab)                   ‐ MEP Non‐Bearing wall rough‐in (above slab) Issues Resolved Contractor COVID‐19 Protocols provided and implemented onsite Coordination with PPL to confirm service connections.

Contract Phases M-A M J-F

J-F M-A M-J J-A S-O N-D

Paid to Date $                       $                       $                       $                      

Contract General Contractor: Sketon Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]

Contract Amount

1,081,000 $                                      1,779,500 $                                      9,680,000 $                                      1,139,000 $                                      91,929 $                                            3,958,464 $                                      908,850 $                                         13,771,429 $                                   

$

Total Total Soft Costs: Current Remaining Project Contingency

$                      

Report Submission Date: 

September  2020

Report Author:

Kim LaBrake

2021

2022

Status Comments

M-J J-A

S-O N-D

J-F M-A M-J

J-A S-O N-D

% Complete

85%

Each schedule task extended 6 weeks

100%

30% 25%

2%

30% 0% 0%

s FP1 & B1  2020 ‐2021

Status Comments

M-J J-A

S-O N-D

J-F M-A M-J

J-A S-O N-D

% Complete

85% Mezzanine stair and floor slab installation 

100%

25%

85% Misc. steel at Cells to be installed in coordination with bearing walls

100%

5% 50%

45% 100%

4%

30%

30% Banks graded at rear of Maintenance Building

Issues in Progress

Executed Change  Orders 17,088 $                     ‐ $                           ‐ $                           ‐ $                          

Original Material  Allowance 164,850 $                     28,800 $                       61,380 $                       17,375 $                       6,000 $                          278,405 $                    

Remaining Material Allowance 147,947 $                                      28,800 $                                        61,380 $                                        17,375 $                                        ‐ $                                              255,502 $                                     

e (with 10% retained)

3,451,156 146,808 243,814 286,580

66,494

$

1,143

4,194,850

18,231 $                    

Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President

Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member

Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor

Made with FlippingBook flipbook maker