Whitehall Municipal Campus Improvements Whitehall Township
Construction Manager
WHITEHALL MUNICIPAL CAMPUS Whitehall Township
DEI Project No.719001 Monthly Progress Report No.05 September 2020
Work Completed
• Phase 2: Construction of Public Works Storage Building, Construction of Police Addition, Demolition of Existing Garages, Prepare subgrade/grade for Surrounding Parking Lots and Roads • Start: August 2020 • Completion of Phase: April 2021 Phase 2: Public Works Facility, Building Area B2.1-B2.18
WORK COMPLETED - Police Addition Phase 2
• Completed CMU bearing walls for Police Addition Building Area 2 • Completed Second Floor Concrete Slabs • Temporary partitions previously installed in existing building are being maintained to keep building weathertight
Police Addition Exterior Framing
• Installed metal stairs to mezzanine • Installed lights and fire alarm devices • Installed cold form framing • Installed sub framing for ceiling construction under mezzanine • Grade banks behind Public Works Storage Building Maintenance Storage
• Prepare new parking areas and loop road for paving WORk IN progress - Site
First Floor Vapor Barrier in Police Addition
• First Floor Concrete Slab Pours • MEP Rough-In of MasonryWalls • Install Door Frames Police Addition WORk IN progress - Site
September 2020
Work In progress
WORK IN PROGRESS - Police Addition Phase 2 continued
• Installation of Structural Wood Deck in Lobby • Installation of Roof Drain Piping Second Floor • Connection of Roof Drain Piping First Floor • Installation of temporary lighting
• Install Steel Lentils in MasonryWalls for Duct Openings • Installation of Hangers for Mechanical Piping Second Floor • Installation of Hangers for HVAC Ductwork Second Floor • Installation of Plumbing Fixture Carriers Second Floor • Construction of Exterior Masonry Mock-up Panel for review and approval • Coordination of New SECTV Cable and Data Service
Structural Wood Decking In Entrance Lobby
Public Works Mezzanine Stair
Cell Block Area
Graded Banks at Maintenance Building
September 2020
Renders
September 2020
Site PLan
September 2020
Floor PLan
First Floor Plan
Second Floor Plan
September 2020
Whitehall Township Project Name: Municipal Campus Improvements Project Number: 719001
2020
Overall Project Schedule Status
J-F
M-A M
J-F M-A M-J J-A S-O N-D
Construct New Public Works Facility Construct Police Addition Phase 1 ‐ Foundations & Building Pad Construct Police Addition Phase 2 ‐ Complete Addition Except Finishes Demolition of Existing Garage Buildings Renovate Existing Township Building Police Addition Phase 2 ‐ Final Finishes Site Work Substantial Completion / Final Completion Construct New Public Works Facility Police Addition Phase 1 Police Addition Phase 2 ‐ Structural steel erection Current Phase and Schedule Status ‐ Exterior Cold Form Framing ‐ 2nd Floor Concrete Slabs ‐ 1st Floor Concrete Slabs Township Office move Demolition of Existing Garage Buildings Site Work ‐ MEP Bearing wall rough‐in (above slab) ‐ MEP Non‐Bearing wall rough‐in (above slab) Issues Resolved Contractor COVID‐19 Protocols provided and implemented onsite Coordination with PPL to confirm service connections.
Contract Phases M-A M J-F
J-F M-A M-J J-A S-O N-D
Paid to Date $ $ $ $
Contract General Contractor: Sketon Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: [Prism Response, LLC]
Contract Amount
1,081,000 $ 1,779,500 $ 9,680,000 $ 1,139,000 $ 91,929 $ 3,958,464 $ 908,850 $ 13,771,429 $
$
Total Total Soft Costs: Current Remaining Project Contingency
$
Report Submission Date:
September 2020
Report Author:
Kim LaBrake
2021
2022
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
85%
Each schedule task extended 6 weeks
100%
30% 25%
2%
30% 0% 0%
s FP1 & B1 2020 ‐2021
Status Comments
M-J J-A
S-O N-D
J-F M-A M-J
J-A S-O N-D
% Complete
85% Mezzanine stair and floor slab installation
100%
25%
85% Misc. steel at Cells to be installed in coordination with bearing walls
100%
5% 50%
45% 100%
4%
30%
30% Banks graded at rear of Maintenance Building
Issues in Progress
Executed Change Orders 17,088 $ ‐ $ ‐ $ ‐ $
Original Material Allowance 164,850 $ 28,800 $ 61,380 $ 17,375 $ 6,000 $ 278,405 $
Remaining Material Allowance 147,947 $ 28,800 $ 61,380 $ 17,375 $ ‐ $ 255,502 $
e (with 10% retained)
3,451,156 146,808 243,814 286,580
66,494
$
1,143
4,194,850
18,231 $
Integration Team Michael Harakal, Mayor John (Jack) Meyers, Deputy Mayor Michael Marks, Chief of Police Tim Christman, Building & Grounds Lee Rackus, Chief of Development Board of Commissioners Philip Ginder, President Joesph Marx, Jr., Vice President
Thomas Slonaker, Secretary Jeffrey J. Warren, Member Charles G. Fisher, Member Randy Atiyeh, Member Michael Dee, Member
Design & Construction Team KCBA Architects, Architect / Structural Engineer Snyder Hoffman, MEP Engineer Terraform Engineering, LLC, Site / Civil Engineer D’Huy Engineering, Inc., Construction Manager Skepton Construction, Inc., General Contractor JBMMechanical, Inc., HVAC Contractor JBMMechanical, Inc., Plumbing Contractor Boro Construction, Electrical Contractor