Upper Providence Township

New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.23, P1.26m P1.27

Install Ceiling Grid & Hard Ceilings (01/25/22) Install Ceiling Mounted Devices (01/31/22) Ongoing: P1.24 – P1.32 Complete Fire Alarm, Security System (02/04/22) Install Floor Finishes (02/18/22) Casework (02/10/22) Floor Finishes (02/18/22)

Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete placement of front and rear concrete aprons. • Complete sidewalk stone preparation. Site Construction Progress

Building Construction Progress

• Complete exterior stone and brick veneer. • Begin edge metal, fascia, and gutter installation. • Begin exterior insulation and metal panel installation. • Complete rough-ins of mechanical, plumbing, gas pipe, electrical systems. • Complete sprinkler rough-ins. • Complete electrical branch wiring. • Installation of window frames and glazing nearing completion. • Complete ceiling grid perimeters and bulkhead layouts. • Complete mechanical and plumbing insulation. • Begin casework and ceramic tile installation. • Begin MEP fixture installation in the Apparatus Bay. • Continue MEP trim-out in living quarters and training sections.

Made with FlippingBook - Online catalogs