Upper Providence Township
Report Submission Date: December 2021
Report Author: Michael DePodwin Report Submission Date: November 2021
21
2022
J
A S O N
D J
F M A M J
% Complete
Status Comments
Report Author: Michael DePodwin
Resubmittals nearing completion
1
2022
99%
Complete Complete Complete Stabilization of site complete Base and binder paving courses complete. Slab on Grade and Structural Steel complete. Exterior walls complete. Roof weathertight. Interior block wall complete. MEP rough‐in ongoing Interior block filler ongoing. Fence to be completed All light pole bases installed. Light pole installation ongoing Complete Stabilization of site complete Base and binder paving courses complete. Slab on Grade and Structural Steel complete. Final roof metal outstanding Interior block wall complete. MEP rough-in nearing completion First paint coat complete. Grid installation ongoing. MEP fit-out begun. Status Comments Resubmittals nearing completion
100% 95% 99%
A S O N
D J
F M A M J
% Complete
99%
100% 90% 90%
75% 0% 0%
10% 0% 0%
100% 100% 100%
99%
25% 65%
90% 100%
0% 0%
25% 60%
Phase 1 2021
Status Comments
0% 0%
J A S O N D J F M A M J
% Complete
99% 95% 75%
Nearing Completion Waiting on MDP delivery.
Phase 1 2021
Status Comments
A S O N D J F M A M J
% Complete
Block filler and first coat complete.
100% 100%
Complete Complete
90% Nearing Completion
15% To be completed after apparatus bay flooirng 10% 0% To be completed in January 2022 Device installation underway. Roof weathertight. Metal roof and cap sheet outstanding. Complete All system installation ongoing. 5% Ceiling tile edge installation begun.
80%
100%
95% Nearing completion 80% 10% Block filler underway
Issues in Progress
Continue Coordinate ASI 11 work with ETI, ETI's controls subcontractor, and UPT's security vendor. Expedite the installation of PECO gas line and delivery of MDP to have permanent power on site. Continue to monitor Erosion & Sedimentation Controls. Ensure site hours, noise, and lighting are compliant with Township ordinances. 0% Issues in Progress Review cost proposal from ETI regarding low voltage, security, and access control changes. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Ensure site hours, noise, and lighting are compliant with Township ordinances. Continue to track equipment and material procurement to ensure critical path remain on schedule. Executed Change Orders Original Material Allowance
Paid to Date (with 10% retained) Paid to Date (with 10% retained)
Remaining Material Allowance
$ $ $ $ $
184,489 47,807 98,883 64,622 395,800
$ $ $ $ $
8,032,228 482,268 53 ,674 957,604 676,009 734,478 5,664,136
$ $ $ $ $
- - - - -
$ $ $ $ $
389,190 37,920 94,098 47,807 209,365
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
4,818,025
$ $ $ $ $
‐ ‐ ‐ ‐
$ $ $ $ $
209,365
$ $ $ $ $
184,489 47,807
47,80
389,190 37,920 94,098
98,88
476,034
64,622 395,800
6,310,001
‐
0% Submittals
Requests for Information
0%
12% 0% Submittals
0% Requests for Information
Approved Rejected Voided Overdue
0%
Complete Outstanding Voided Overdue
0%
Approved Rejected Voided Overdue
5% 0
13%
Complete Outstanding Voided Overdue
88%
0%
95%
2%
87%
98%