New Central Emergency Services Facility
Projected Progress for Jan. 2022
• Complete installation of exterior brick veneer and stone. • Complete interior stone veneer. • Complete installation of storefront system. • Complete concrete front and rear apparatus bay aprons and sidewalks. • Complete installation of roof and exterior wall metal panels. • Install rear apparatus bay doors. • Begin edge metal, fascia, gutters, and soffits. • Begin casework installation. • Begin resinous floor and ceramic tile installation in living quarters.
• Complete hard ceilings and ceiling grid. • Complete plumbing fixture installation. • Place all grilles, registers, and diffusers. • Place all interior light fixtures.
Resinous flooring installation ongoing.
Exterior brick veneer installation ongoing.