Upper Providence Township New Emergency Services Facility
Report Submission Date: November 2021
Report Author: Michael DePodwin Report Submission Date: November 2021
1
2022
A S O N
D J
F M A M J
% Complete
Status Comments
Report Author: Michael DePodwin
Resubmittals nearing completion
99%
1
2022
Slab on Grade and Structural Steel complete. Final roof metal outstanding Status Comments
100% 95% 95% 99%
A S O N
D J
F M A M J
% Complete
Complete Status Comments All light pole bases installed. Light pole installation ongoing Complete Stabilization of site complete Base and binder paving courses complete. All light pole bases installed. Light pole installation nearing completion Complete Stabilization of site complete Base and binder paving courses complete. Fence to be completed Interior block wall complete. MEP rough‐in nearing completion First paint coat complete. Grid installation begun. MEP fit‐out begun. Slab on Grade and Structural Steel complete. Exterior walls complete. Roof weathertight. Interior block wall complete. MEP rough‐in ongoing Interior block filler ongoing. Resubmittals nearing completion
50% 0% 0%
100 9 9
25% 60% 90% 100% 99% 0% 0% 25% 60% 95% 100% 100% 10% 0% 0% 100% 100% 0% 0%
Phase 1 2021
A S O N D J F M A M J
% Complete
Complete Complete
Phase 1 2021
All systems placed. Rough‐in and insulation nearing completion Status Comments
95%
A S O N D J F M A M J
% Complete
95% Waiting on MDP delivery.
100%
Complete Complete
15% Ceiling grid perimeter and framing for hard ceilings underway. 75% 5% Device installation underway. Block filler and first coat complete. 80% Roof weathertight. Metal roof and cap sheet outstanding. Complete All system installation ongoing. 100% 100% Complete 100%
95% Nearing completion 80% 10% Block filler underway
Issues in Progress
Coordinate ASI 11 work with ETI, ETI's controls subcontractor, and UPT's security vendor. Begin to gather closeout documentation from all Contractors. Continue to monitor Erosion & Sedimentation Controls. Ensure site hours, noise, and lighting are compliant with Township ordinances. 0% Issues in Progress Review cost proposal from ETI regarding low voltage, security, and access control changes. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Ensure site hours, noise, and lighting are compliant with Township ordinances. Continue to track equipment and material procurement to ensure critical path remain on schedule. Executed Change Orders Original Material Allowance
Paid to Date (with 10% retained)
Remaining Material Allowance
7,042,721 4,818,025 482,268 779,979 545,379 646,751 5,070,611
$ $ $ $ $
‐ ‐ ‐ ‐ ‐
$ $ $ $ $
389,190 37,920 209,365 47,807 94,098 47,807 209,365 389,190 37,920 94,098
$ $ $ $ $
184,489 47,807 98,883 64,622 395,800 47,807 98,883 64,622
Paid to Date (with 10% retained)
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
$ $ $ $ $
‐ ‐ ‐ ‐
$ $ $ $ $
$ $ $ $ $
184,489
533,674 476,034
6,310,001
‐
395,800
87% 0% Submittals 0% Submittals
100% Requests for Information Requests for Information 0%
0%
Approved Rejected Voided Overdue
0%
13%
Complete Outstanding Voided Overdue Complete Outstanding Voided Overdue
0%
0%
Approved Rejected Voided Overdue
0%
13%
0%
2%
87%
98%