Upper Providence Township New Emergency Services Facility
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.20 Complete Interior Walls (11/19/21) Complete Plymavent System (11/23/21) Complete Roof – Roof Watertight (11/29/21) Ongoing: P1.21 – P1.26 Plumbing & Sprinkler Rough-in (12/09/21) Complete Painting of Walls (12/23/21) Complete MEP System Placement (12/23/21)
Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Begin grading of interior loop road. • Continue light pole base installation. Site Construction Progress
Building Construction Progress
• Complete masonry wall and in-wall rough-in. • Complete sprayfoam insulation. • Continue overhead rough-ins of mechanical, plumbing, gas pipe, electrical, and fire alarm. • Complete rough-in of sprinkler mains. • Electrical branch wiring nearing completion. • Complete installation of Plymavent exhaust system. • Complete exterior metal framing and sheathing. • Complete installation of hot-applied roof. • Begin installation of window frames and glazing. • Install temporary doors and windows in preparation of temporary heating.
• Begin ceiling grid perimeters and bulkhead layouts. • Continue mechanical and plumbing insulation. • Begin exterior brick veneer installation.