Northampton Township
Report Submission Date:
10/24/22
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
Report Author: Colin Case
2023
Status Comments
N-D J-F M-A M-J J-A S-O N-D
% Complete
Overall Project Schedule Status
In progress: Building demolition and new building pad complete.
20%
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roo P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Ca MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Pun P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Co Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidew P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Co P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems P1.24 ‐ Energize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid and Complete Hard Ceilings Issues Resolved Work with Vision Mechanical on resolving sprinkler Coordinate with Lobar on roof nail board and stone Coordinate the FF&E process with GKO and the Tow Complete building low voltage, security, and access Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Current Phase and Schedule Status
5% July 2022 thru July 2023
Nearing completion. The apparatus bay slab remains incomplete and will be poured after the slab on deck
90%
50% Steel super structure complete.
December 2022 thru January 2023
February 2023 thru April 2023
March 2023 thru April 2023
March 2023 thru April 2023
May 2023 thru July 2023
June 2023 thru July 2023
2022 - 2023
Status Comments
J A S O N D J F M A M J J
% Complete
80% Utility and stormwater work remain in progress
20%
Building pad Completed. Retaining walls in progress.
Nearing completion. The apparatus bay slab remains incomplete and will be poured after the slab on deck
90%
50% Steel super structure complete.
Issues in Progress
Other Discussion
The GC's trusses were designed to be loading bearing on the stair towers and elevator. A5 is providing details to remediate the situation without the need to refabricate the trusses.
Printed 10/25/2022 1 of 1