Report Submission Date:
05/31/22
Report Author:
Colin Case
2023
Status Comments
F M ‐ A M ‐ J ‐ J A
‐ S O
‐ N D
% Complete
10% In progress: Building demolition completed
July 2022 thru July 2023
July 2022 thru September 2023
September 2022 thru November 2022
November 2022 thru January 2023
January 2023 thru March 2023
February 2023 thru April 2023
March 2023 thru May 2023
April 2023 thru July 2023
July 2023
ase Sitework 2022 ‐ 2023
Status Comments
S O N D J F M A
% Complete
100% Completed
Demolition, Temporary fencing, power, construction trailer and staging areas completed.
60%
10% Building pad construction underway.
Issues in Progress Scheduling all Cell Service providers to relocate all cell tower utilities.