NEW FIRE STATION #3 AND NEW FIRE STATION #73 Northampton Township DEI Project No. 721001 Monthly Progress Report No. 4 October 2022
NEW FIRE STATION #3 AND NEW FIRE STATION #73
FIRE STATION #3 Current Site Milestones: S3.12-S3.15: (7/22 – 11/22) Current Building Milestones: B3.3-B3.7: (11/22-12/22)
Station #3 Aerial
FIRE STATION #73 Site Milestones: S73.10-S73.14: (7/22 – 8/22) Building Milestones: B73.5-B73.7: (10/22-12/22)
Station #73 Aerial
October 2022
NEW FIRE STATION #3 AND NEW FIRE STATION #73
WORK COMPLETED STATION #3
• Continued submission and review of shop drawings and submittals. • Continued procurement of items with long lead times. • Completed 3D modeling and coordination drawings. • Continued Pre-installation meetings for upcoming work as required. • Continued to maintain construction entrances and maintain erosion & sediment control measures. • Continued to work with PECO to establish the new electrical service. • Coordinated the natural gas installation schedule with PECO. • Completed relocation of the Comcast communication line along Township Road. • Continued site clearing. • Completed bulk excavation and clean fill haul-off. • Completed Underground Basin B1. • Continued Site retaining wall installation. • Completed Underpinning work for the Cell Tower foundations.
• Completed the building pad. • Completed all foundations. • Completed CMU foundation Block. • Completed Mechanical, Plumbing, & Electrical underground.
• Began Structural Steel Erection. • Received AHUs and RTU curbs.
Station #3 Underground Basin B1
Station #3 Steel Super Structure
Station #3 Site Retaining Wall
WORK COMPLETED STATION #73
• Continued submission and review of shop drawings and submittals. • Continued procurement of items with long lead times. • Completed 3D modeling and coordination drawings. • Continued Pre-installation meetings for upcoming work as required. • Continued to maintain construction entrances and maintain erosion & sediment control measures. • Continued to work with PECO to establish the new electrical service. • Coordinated the natural gas installation schedule with PECO. • Continued site clearing. • Completed bulk excavation and clean fill haul-off. • Completed Underground Basin B1. • Continued Site retaining wall installation. • Installed the Oil Separator. • Completed the Transformer pad.
• Completed the building pad. • Completed all foundations. • Completed CMU foundation Block. • Completed Mechanical, Plumbing, & Electrical underground. • Completed Structural Steel Erection.
• Completed Metal Decking. • Received RTUs and curbs.
Station #73 Underground Basin B1
Station #73 In Wall Plumbing Rough-Ins
#73 Slab on Deck Preparation
October 2022
NEW FIRE STATION #3 AND NEW FIRE STATION #73
Station #3 Steel Erection
Station #3 Garage Bay Trench Drains
Station #3 Metal Decking
Station #73 Slab on Grade Pour
Station #73 Electrical Rough ins
Station #73 Elevator Pit
October 2022
Building Layout: Station #3
October 2022
Building Layout: Station #73
October 2022
Station #3
Northampton Township Fire Station #3 Project Number: 721001
2022
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D
Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B3.1 to B3.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. B3.5 to B3.7 ‐ Erect structural steel. Complete masonry walls. Complete roof (building to be watertight).
B3.8 to B3.12 ‐ Complete interior CMU walls, metal studs. Complete in ‐ wall MEP rough ‐ ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough ‐ ins.
B3.13 to B3.16 ‐ Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B3.17 to B3.20 ‐ Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B3.21 to B3.23 ‐ Complete fire alarm and security system. MEP start ‐ up.. Complete elevator inspection. B3.24 to B3.27 ‐ Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B3.28 to B3.30 ‐ Substantial completion, Final completion. Owner furniture, fixtures and equipment move ‐ in and occupy. S3.1 to S3.6 ‐ NTP,process shop dwgs/submittal/begin procurement Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence,protect communication tower, install staging area,construction entrance,construction trailers,temp. S3.7 to S3.11 ‐ Demo existing fire station incl footings, foundations. Provide protection for cell town bldg. Fill void from basement. Route new utilities for tower. Inst. Stormwater basin and storm sewer piping. S3.12 to S3.15 ‐ Prepare bldg pad, inst. Undergrnd electric, gas to bldg. pad. Inst. San. Sewer/water piping and connect to street S3.16 to S3.18 ‐ Complete rough grading, inst. ret. walls, ext. light bases, post, lights. Inst. concrete curbs/sidewalks incl. work along Township Road. B3.1 to B3.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. B3.5 to B3.7 ‐ Erect structural steel. Complete masonry walls. Complete roof (building to be watertight). Current Building Phase: Current Site Phase: Current Phase and Schedule Status
Milestones have been adjusted to account for the 30 ‐ day Owner mov
F M A M J
J
Issues Resolved
Underpinning of existing cell tower was completed on 9/1 New electrical service will be run under the road rather than overhead to the site.
Report Submission Date:
10/24/22
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
Report Author:
Colin Case
2023
Status Comments
J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D
% Complete
Overall Project Schedule Status
30% Building Pad Completed
July 2022 thru July 2023
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roo P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Ca MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Pun P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Co Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidew P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Co P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems P1.24 ‐ Energize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid and Complete Hard Ceilings Issues Resolved Work with Vision Mechanical on resolving sprinkler Coordinate with Lobar on roof nail board and stone Coordinate the FF&E process with GKO and the Tow Complete building low voltage, security, and access Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Current Phase and Schedule Status
Foundations and underground M.E.P. complete. Slab on grade to be poured after structural steel completes.
90%
25% Steel erection is in progress.
November 2022 thru January 2023
January 2023 thru March 2023
February 2023 thru April 2023
March 2023 thru May 2023
April 2023 thru July 2023
July 2023
veout extension and adjusted milestones per the GC's CPM schedule.
2022 ‐ 2023
Status Comments
A S O N D J F M A
% Complete
100% Completed
Basin B1 completed. New utilities to be installed during the month of November.
75%
20% Building Pad Completed
60%
Foundations and underground M.E.P. complete. Slab on grade to be poured after structural steel completes.
90%
25% Steel erection is in progress.
Issues in Progress
Other Discussion
Cell Service providers have not provided a relocation schedule for their utilities serving the cell tower building PECO has not provided a installation scheudule for the electric or gas services
Printed 10/25/2022 1 of 1
Station #73
Northampton Township Fire Station #73 Project Number: 721001
2022
Overall Project Schedule Status
J-F M-A M-J J-A S-O
Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B73.1 to B73.4 - Place foundations. Complete under slab MEP rough-in. Complete slab on grade and cure time. B73.5 to B73.7 - Erect structural steel. Complete exterior masonry walls. Complete roof (building to be watertight). B73.8 to B73.12 - Complete interior CMU walls, metal studs. Complete in-wall MEP rough-ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough-ins. B73.13 to B73.16 - Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B73.17 to B73.20 - Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B73.21 to B73.24 - Complete fire alarm and security system. MEP start-up. Relocated offices from trailers to inside bldg. Complete elevator inspection. B73.25 to B73.28 - Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B73.29 to B73.31 - Substantial completion, Final completion. Owner furniture, fixtures and equipment move-in and occupy. S73.5 to S73.9 - Demo existing fire station incl footings, foundations and existing underground fuel oil tank. Install staging area, construction entrance, construction trailers, temporary, power, site lighting and communication from existing utilities. EC provide temporary overhead connections. Route new utilities for Verizon bldg. Install stormwater basin and connect to street and storm sewer piping to basin. S73.10 to S73.14 - Prepare bldg. Pad, install underground electric and gas to bldg. Pad. Install sanitary piping. Sewer piping connect to street pipe. Complete rough grading, install retaining walls. B73.1 to B73.4 - Place foundations. Complete under slab MEP rough-in. Complete slab on grade and cure time. B73.5 to B73.7 - Erect structural steel. Complete exterior masonry walls. Complete roof (building to be watertight). Current Building Phase: Current Phase and Schedule Status Current Site Phase:
F M A M J
Issues Resolved
Coordinated with PECO to raise the low-hanging electric lines at the rear entrance of the site.
Report Submission Date:
10/24/22
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
Report Author: Colin Case
2023
Status Comments
N-D J-F M-A M-J J-A S-O N-D
% Complete
Overall Project Schedule Status
In progress: Building demolition and new building pad complete.
20%
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roo P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Ca MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Pun P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Co Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidew P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Co P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems P1.24 ‐ Energize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid and Complete Hard Ceilings Issues Resolved Work with Vision Mechanical on resolving sprinkler Coordinate with Lobar on roof nail board and stone Coordinate the FF&E process with GKO and the Tow Complete building low voltage, security, and access Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Current Phase and Schedule Status
5% July 2022 thru July 2023
Nearing completion. The apparatus bay slab remains incomplete and will be poured after the slab on deck
90%
50% Steel super structure complete.
December 2022 thru January 2023
February 2023 thru April 2023
March 2023 thru April 2023
March 2023 thru April 2023
May 2023 thru July 2023
June 2023 thru July 2023
2022 - 2023
Status Comments
J A S O N D J F M A M J J
% Complete
80% Utility and stormwater work remain in progress
20%
Building pad Completed. Retaining walls in progress.
Nearing completion. The apparatus bay slab remains incomplete and will be poured after the slab on deck
90%
50% Steel super structure complete.
Issues in Progress
Other Discussion
The GC's trusses were designed to be loading bearing on the stair towers and elevator. A5 is providing details to remediate the situation without the need to refabricate the trusses.
Printed 10/25/2022 1 of 1