New Upper Dublin Middle School
Animated publication
Monthly Construction Manager’s Report
NEW SANDY RUN MIDDLE SCHOOL Upper Dublin School District
DEI Project No.280010 Monthly Progress Report No.08 March, 2020
Site Work Ongoing
Staging Area
Storm Water Management Installation Continues
March 2020
• The site has been cleared and soil stockpiled. • Storm water piping installation is ongoing. • Underground basin A1 is complete. • The contractor staging area is complete. • Temporary power lines to job trailers has been completed and inspected. • Set up of the temporary office trailers has competed. • The new domestic water meter pit has been approved and is being procured for installation during Spring Break.
March 2020
Work Ongoing - Site
March 2020
• Concrete foundation footings are continuing into the main building area • Concrete foundation footings in the Classroom Wing have completed. • The building retaining wall is more than 80% complete. • Exterior masonry walls are continuing weather pending. • Plumbing and electrical underground rough in is ongoing and being inspected by UDT as requested. • Structural steel began March 4th and will be ongoing until complete. • Joists and deck have competed for Area A first floor. • Concrete is scheduled to be placed on the elevated deck in March. • MEP prime contractors are scheduled to continue rough in of utilities in floor and walls as coordination continues. • Both elevator shaft pits have been installed complete with damp proofing.
Steel Columns Set in Classroom Wings
Retaining Wall Continues as Steel is Set
March 2020 Retaining Wall Footing
Work Ongoing - Site
Classroom Masonry Walls
Planetarium Retaining Walls Begin
CMU Walls Classroom Area B Underway
Structural Steel Begins
Masonry Bearing Walls
Classroom Wing Structural Steel
March 2020
Drone Photo
March 2020
School District: Upper Dublin School District Project Name: Sandy Run Middle School Project Number: 280010
2019
Overall Project Schedule Status
J/A/S O/N/D J/F/M A
New Building Site Construction Phase S2B S2B.8‐S2B.18: water meter pit/dom.&fire lines, driveway conn.,emer.gen feed/san.pipe/ret walls/backfill soil/grass paver S2B19‐S2B.23: Install walkways, relocate const. trailers, remove temp rock const. entrance, new multi‐purpose and ball fields Building Construction Phase 2B 2B.1 ‐ 2B.2 Stone Classroom Building pad 2B.3 Stone Main Building Pad 2B.4 MEP Underground rough in classroom wing 2B.5 Concrete slab on grade classroom wing 2B.6 ‐ 2B.7 Main building foundations, MEP underground rough in, masonry and structural steel 2B.8 ‐ 2B.10 Classroom ground floor masonry, structural steel and concrete deck 2B.11 ‐ 2B.15 Classroom 1st, 2nd floor and roof masonry, structural steel and concrete deck 2B.16 ‐ 2B.18 Main Building masonry, structural steel and concrete deck 2B.19‐2B31: Exterior shell, masonry, inst. Fireproofing,,MEP above ceiling,int. partitions MEP rough‐in, wall finishes, floor finishes, ceiling grid,MEP ceiling equip, energy permanent power 2B.32‐2B.38: Equipment start‐up, commissioning, punchlist, substantial completion, district clean‐up and move‐in Western Building and Site Construction Phase 3 (6/15/22 ‐ 8/25/22) S3.1 ‐ S3.14: Sitework, demo of southern portion of existing building, modulars removal an temporary driveway installation Western Building and Site Construction Phase 4 (8/25/22 ‐ 6/15/23) S4.1 ‐ S4.21: Sitework, demo in entirety of existing building, installation of parking lots and driveways Site Construction Phase 5 (6/15/23 ‐ 8/15/23) S5.1‐S5.9: Sitework: Final grade and seeding, final paving and landscaping installation
2019
Current Phase and Schedule Status
J/A/S O/N/D J/F/M A
Site Construction Phase S2A & S2B Site Construction Phase S2A has been completed S2B.8 ‐ S2B.9 Install new meter pit and domestic water and fire lines. Remove existing meter pit. S2B.1‐S2B.7: Classrm wing blg. pad, re‐route sanitary, u/g water service, main wing subgrade, comp u/g utility rough‐in
Issues Resolved 1. The new water meter pit will be installed during the week of Spring Break to reduce the impact on students and staff (there will be no water to the existing middle school th
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: Boro Construction Electrical Contractor: Boro Construction Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.
Contract Amount
2,000, $ 11,426, $ 59,463, $ 6,280, $ 410, $ 6,748, $ 43,158, $ 2,867, $
Total Total Soft Costs: Current Remaining Project Contingency
G:\Projects\006-299 - Schools\280 - Upper Dublin SD\280010 - Sandy Run MS\Payments & Change Orders\Contract Status and Payment Log_280010.xlsx
Report Submission Date:
March 2020
Report Author:
Zach Zazo
2020
2021
2022
2023
Status Comments
% Complete
A/M/J J/A/S O/N/D J/F/M A/M/J J/A/S O/N/D J/F/M A/M/J J/A/S O/N/D J/F/M A/M/J J/A/S
0% 0%
0% 0% 30% 80% 80% 60%
0% 0%
0% 0%
0%
0%
0%
2020
2021
2022
2023
Status Comments
% Complete
A/M/J J/A/S O/N/D J/F/M A/M/J J/A/S O/N/D J/F/M A/M/J J/A/S O/N/D J/F/M A/M/J J/A/S
Complete
100%
Scheduled for Spring Break
0%
Complete. New utilities are underway.
45%
Issues in Progress
1. Final PA DOT and UDT inspections and approvals underway for the completed Twining Road Widening and PA DOT signal and ADA ramps work at SR 152 and Twining Road.
he week of April 6th through the 10th).
Remaining Material Allowance 485,070 $ 234,870 $ 252,090 $ 111,380 $ 11,680 $ 1,095,090 $
Original Material Allowance 479,000 $ 234,870 $ 252,090 $ 25,000 $ 111,380 $
Paid to Date (with 10% retained)
Executed Change Orders
,000 ,590 ,370 ,000 ,000 ,000 ,370 ,000
494,325 $ 155,313 $ 176,994 $ 7,062,112 $ 128,160 $ 6,107,320 $
‐ $ 9,250 $ ‐ $ 13,338 $ ‐ $ 4,088 $
$
1,102,340
Dr. Steven M. Yanni, Superintendent Andrew Lechman, Business Administrator Robert Lester, Director of Facilities Dr. Jill Parker Clark, Principal School Board Amy Francek, President Darlene Davis, Vice President Michael Henderson
Jennifer Iannitti Art Levinowitz Stanley J. Ropski Titia Scherpbier Mark Sirota Jeffrey Wallack
Construction Manager D’Huy Engineering, Inc. Project Architect Breslin Ridyard Fadero Architects Contractors Skepton Construction, Inc. General Construction Boro Construction Mechanical Construction Boro Construction
Electrical Construction JBM Mechanical, Inc. Plumbing Construction
Made with FlippingBook Ebook Creator