New Lehigh Elementary School
School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034
2019
Overall Project Schedule Status
J‐F M‐A M‐J J‐A S‐O N‐D
Site Milestones 1S.1 ‐ 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT ‐ 4/30 1S.3 ‐ 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 ‐ 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 ‐ 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 ‐ 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 ‐ 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 ‐ 2BS.8: Topsoil install, painting of lots and drives 3S.1 ‐ 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 ‐ 3S.7: Abatement, installation of access roads and parking lots 4S.1 ‐ 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 ‐ 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 ‐ 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1‐1B.3 ‐ Prelim prep work, excavation & site, footings & foundations
1B.4 ‐ Load bearing CMU 1B.5 ‐ Exterior wall finishes
1B.6‐1B.8 ‐ Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9‐1B.12 ‐ Construction of interior walls, MEP rough‐ins and equipment installation 1B.13‐1B.16 ‐ Interior & floor finishes, equipment start‐up & commissioning, exterior finishes.
1B.17‐1B.19 ‐ Contractor cleanup and punchlist 1B.20‐1B.21 ‐ District cleanup, setup and move in
2020
2020
M J
J A S O
1B.5‐1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 2BS.2: Installation of stormwater conveyance, septic system and fire protection storage tank. 1B.10‐1B.12: HVAC/plumbing equipment and electrical systems installation 2BS.4‐2BS.8: Construct new fire lane, curbing, sidewalks, binder course and parking lots 1B.13‐1B.14 ‐ Ceiling and interior paint, floor finishes, VDB installation Current Phase and Schedule Status ‐ Site Phase 2B and Building Phase 1
Issues Resolved
5,499,330 $ 1,248,759 $ 29,289,026 $ 4,080,000 $ 1,663,000 $ 118,026 $ 20,087,000 $ 3,341,000 $ Contract Amount
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.
Total Total Soft Costs: Current Remaining Project Contingency:
G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034.xlsx