New Lehigh Elementary School
Animated publication
Construction Manager
NEW LEHIGH ELEMENTARY SCHOOL Northampton Area School District
DEI Project No.022034 Monthly Progress Report No.13 May 2020
Work Completed
• Phase 2B: Exterior veneer, roof structure and deck, interior wall construction, MEP equipment installation, interior finishes. • Start: April 15,2019 • Completion of Phase: June 15,2021 Phase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.
• The GC has completed all interior concrete floor slabs. Interior wall construction has commenced in the main office and kitchen area. • Exterior finishes including the brick veneer, aluminum store fronts and curtain walls and sof fit cladding systems are under way at the exterior of Areas B and C. • MEP contractors have begun installing and wiring VAV units in the 2nd floor classrooms and corridors of Areas B and C. Work Completed - Site
• The remaining load bearing CMU in the main entrance lobby is underway and nearing completion. • Brick veneer on high rising walls above the flat roof in Area A is underway. • Roof drains on all flat roofs have been assembled. Roofing to begin early June. • Rough-ins for the kitchen have been completed. • Installation of electrical systems and cabling are underway in Areas B and C classrooms and corridors. Ceiling grid to begin mid-June.
Continuation of exterior finishes and curtain wall assemblies.
Completion of interior floor slabs throughout the building.
• Exterior concrete in the courtyard area has begun. • The GC starting to tie-in the new bus entranceway and begin the expansion of the faculty parking lot. Work Completed - Building
Interior finishes including the corridor wall tile and hard ceiling area
MEP installation on the 2nd floor of Area B and C
May 2020
Site Layout
Building Layout First Level
Building Layout Second Level
May 2020
Renders
May 2020
Aerial Shot
May 2020
School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034
2019
Overall Project Schedule Status
J‐F M‐A M‐J J‐A S‐O N‐D
Site Milestones 1S.1 ‐ 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT ‐ 4/30 1S.3 ‐ 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 ‐ 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 ‐ 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 ‐ 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 ‐ 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 ‐ 2BS.8: Topsoil install, painting of lots and drives 3S.1 ‐ 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 ‐ 3S.7: Abatement, installation of access roads and parking lots 4S.1 ‐ 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 ‐ 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 ‐ 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1‐1B.3 ‐ Prelim prep work, excavation & site, footings & foundations
1B.4 ‐ Load bearing CMU 1B.5 ‐ Exterior wall finishes
1B.6‐1B.8 ‐ Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9‐1B.12 ‐ Construction of interior walls, MEP rough‐ins and equipment installation 1B.13‐1B.16 ‐ Interior & floor finishes, equipment start‐up & commissioning, exterior finishes.
1B.17‐1B.19 ‐ Contractor cleanup and punchlist 1B.20‐1B.21 ‐ District cleanup, setup and move in
2020
2020
M J
J A S O
1B.5‐1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 2BS.2: Installation of stormwater conveyance, septic system and fire protection storage tank. 1B.10‐1B.12: HVAC/plumbing equipment and electrical systems installation 2BS.4‐2BS.8: Construct new fire lane, curbing, sidewalks, binder course and parking lots 1B.13‐1B.14 ‐ Ceiling and interior paint, floor finishes, VDB installation Current Phase and Schedule Status ‐ Site Phase 2B and Building Phase 1
Issues Resolved
5,499,330 $ 1,248,759 $ 29,289,026 $ 4,080,000 $ 1,663,000 $ 118,026 $ 20,087,000 $ 3,341,000 $ Contract Amount
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.
Total Total Soft Costs: Current Remaining Project Contingency:
G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034.xlsx
Report Submission Date: May 2020
Report Author: M. Evans
2020
2021
Status Comments
% Complete
D J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D
95% 100% 100% 90%
Bus driveway base paving and curbing is completed. Parking lot work to be completed in Summer 2020 Utility work under parking lot to be completed in Summer 2020
5% 0%
60%
0% 0% 0% 0% 0% 0% 0% 0%
Phases are scheduled for Sept. 2021 through Jan. 2022
Phase is scheduled for May 2022 Phases are scheduled for June ‐ July 2022 Phases are scheduled for August 2022
60% 50% 95% 65% 15% 95% Insulation, brick veneer and curtainwall ongoing. B/C Shingle ongoing. Low roof ongoing. Load bearing CMU to be completed June. MEP roughs complete and equipment install is ongoing. Footings and foundations 100% complete. Storm tie‐in remaining. Wall paint in 1st/2nd floor B/C underway, hard ceilings B/C ongoing. 0% Substantial Completion 5/16/21.
0%
2021
Status Comments
N D J F M A M J
J A S O
% Complete
Exterior wall finishes, curtainwall and storefronts ongoing. Septic tanks and piping installed to existing drainfield.
70% 75% 60% 30% 40%
MEP rough‐ins complete. Wiring, piping and ductwork install underway. Base coat on new entranceway complete for add'l parking. Block fill and primer on 1st/2nd corridor walls and hard ceiling install.
Issues in Progress
PennDOT permit application submitted. Request conditional permit to be issued by June 5th.
Reviewing schedule for critical tasks to keep project on track.
16,242,058 $ ‐ $ 1,214,476 $ 1,145,059 $ 1,807,844 $ 12,074,679 $ Paid to Date (with 10% retained)
Remaining Material Allowance 173,579 $ 48,063 $ 100,147 $ 51,819 $ 9,350 $ 382,957 $
(101,300) $ ‐ $ ‐ $ ‐ $ ‐ $ (101,300) $ Executed Change Orders
487,900 $ 9,350 $ 113,400 $ 56,375 $ 53,150 $ 255,625 $ Original Material Allowance
Mr. Joseph S. Kovalchik, Superintendent Mr. Terry Leh, Business Administrator Mr. Jonathan Jenny, Director of Maintenance Mrs. Cassandra Herr, Principal School Board David Gogel, President Charles Frantz, Vice President Dr. Michael Baird
John Becker James Chuss Charles Longacre Roy Maranki Robert Mentzell Ross Makary
Construction Manager D’Huy Engineering, Inc. Project Architect KCBA Architects Contractors Skepton Construction, Inc. General Construction JBM Mechanical, Inc. Mechanical Construction Cyprium Solutions, Inc. Electrical Construction Myco Mechanical, Inc. Plumbing Construction