New Lehigh Elementary School
Report Submission Date: May 2020
Report Author: M. Evans
2020
2021
Status Comments
% Complete
D J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D
95% 100% 100% 90%
Bus driveway base paving and curbing is completed. Parking lot work to be completed in Summer 2020 Utility work under parking lot to be completed in Summer 2020
5% 0%
60%
0% 0% 0% 0% 0% 0% 0% 0%
Phases are scheduled for Sept. 2021 through Jan. 2022
Phase is scheduled for May 2022 Phases are scheduled for June ‐ July 2022 Phases are scheduled for August 2022
60% 50% 95% 65% 15% 95% Insulation, brick veneer and curtainwall ongoing. B/C Shingle ongoing. Low roof ongoing. Load bearing CMU to be completed June. MEP roughs complete and equipment install is ongoing. Footings and foundations 100% complete. Storm tie‐in remaining. Wall paint in 1st/2nd floor B/C underway, hard ceilings B/C ongoing. 0% Substantial Completion 5/16/21.
0%
2021
Status Comments
N D J F M A M J
J A S O
% Complete
Exterior wall finishes, curtainwall and storefronts ongoing. Septic tanks and piping installed to existing drainfield.
70% 75% 60% 30% 40%
MEP rough‐ins complete. Wiring, piping and ductwork install underway. Base coat on new entranceway complete for add'l parking. Block fill and primer on 1st/2nd corridor walls and hard ceiling install.
Issues in Progress
PennDOT permit application submitted. Request conditional permit to be issued by June 5th.
Reviewing schedule for critical tasks to keep project on track.
16,242,058 $ ‐ $ 1,214,476 $ 1,145,059 $ 1,807,844 $ 12,074,679 $ Paid to Date (with 10% retained)
Remaining Material Allowance 173,579 $ 48,063 $ 100,147 $ 51,819 $ 9,350 $ 382,957 $
(101,300) $ ‐ $ ‐ $ ‐ $ ‐ $ (101,300) $ Executed Change Orders
487,900 $ 9,350 $ 113,400 $ 56,375 $ 53,150 $ 255,625 $ Original Material Allowance