•Finished painting the gymnasium ceiling and walls. •Installed back stops, scoreboards and the wrestling mat hoist in the gymnasium. •Continued installation of hydronic piping and equipment in the basement mechanical room. •Continued MEP above ceiling work in the Administration area. •Began installation interior of aluminum storefronts in the administration area. •Began installation of casework and marker boards in the classroomwing. •Began installation of bathroom fixtures. Work in Progress - Building (CONT.)
Casework and markerboards installed in the first-floor classrooms.