New Lehigh Elementary School - October 2020
Animated publication
Construction Manager
NEW LEHIGH ELEMENTARY SCHOOL Northampton Area School District
DEI Project No.022034 Monthly Progress Report No.18 October 2020
Work In Progress
•Phase 2B: Exterior finishes, roof structure and deck, MEP equipment installation and start-up, interior finishes. •Start: April 15, 2019 •Completion of Phase: June 15, 2021 Phase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.
Work in Progress - Building
•Continued installation of exterior metal fascia and soffits. •Completed installation of composite metal panels above window heads. •Completed exterior aluminum curtain wall assemblies. •Completed placement of terrazzo flooring in the 2nd floor classroomwing. •Began installation of lighting control devices in the classroomwing. •Continued interior painting in the classroomwing. •Continued installation of ceiling grid in the classroomwing.
•Began ceramic wall tile in the kitchen. •Installed the kitchen walk-in units.
•Finished painting the gymnasium ceiling and walls. •Installed back stops, scoreboards and the wrestling mat hoist in the gymnasium. •Continued installation of hydronic piping and equipment in the basement mechanical room. •Continued MEP above ceiling work in the Administration area. •Began installation interior of aluminum storefronts in the administration area. •Began installation of casework and marker boards in the classroomwing. •Began installation of bathroom fixtures. Work in Progress - Building (CONT.)
Casework and markerboards installed in the first-floor classrooms.
October 2020
Work in Progress
Work In Progress - Site
•Continued installation of concrete paving. •Continued installation of stormwater conveyance and downspout tie-ins. •Continued installation of exterior site light bases in concrete paving. •Completing installation of the fire protection water storage tank. •Maintained E&S controls.
The flat bituminous roof has been completed.
Placement of concrete paving
Finished paint and equipment installation in the gymnasium.
Installation of the fire protection water storage tank.
Fixture installation in gang bathrooms.
October 2020
Renderings
Building Layout First Level
Building Layout Second Level
October 2020
School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034
2019
Overall Project Schedule Status
J-F M-A M-J J-A S-O N-D
Site Milestones 1S.1 - 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT - 4/30 1S.3 - 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 - 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 - 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 - 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 - 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 - 2BS.8: Topsoil install, painting of lots and drives 3S.1 - 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 - 3S.7: Abatement, installation of access roads and parking lots 4S.1 - 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 - 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 - 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1-1B.3 - Prelim prep work, excavation & site, footings & foundations
1B.4 - Load bearing CMU 1B.5 - Exterior wall finishes
1B.6-1B.8 - Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9-1B.12 - Construction of interior walls, MEP rough-ins and equipment installation 1B.13-1B.16 - Interior & floor finishes, equipment start-up & commissioning, exterior finishes.
1B.17-1B.19 - Contractor cleanup and punchlist 1B.20-1B.21 - District cleanup, setup and move in
2020
2021
O N D J F M
1B.5-1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 1B.10-1B.12, 1B.15: MEP equipment piping and fixture installations 1B.13-1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3-2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 3S.6-3S.7: Finalize installation of bus/service access road and main parking area. Current Phase and Schedule Status - Site Phase 2B and Building Phase 1
Issues Resolved
Contract Amount
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.
$ $ $ $ $ $ $ $
5,499,330 1,248,759 29,289,026 4,080,000 1,663,000 118,026 3,341,000 20,087,000
Total Total Soft Costs: Current Remaining Project Contingency:
G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx
Report Submission Date: October 2020
Report Author: M. Evans
2020
2021
Status Comments
% Complete
D J-F M-A M-J J-A S-O N-D J-F M-A M-J J-A S-O N-D
95% 100% 100% 95% 100% 100%
Parking lot utility work completed.
Bus driveway base paving and curbing is completed. Finalized new parking and service areas. Secure site for school. Parking lot base tie-in complete. Landscaping behind curbs ongoing.
75% 25%
0% 0% 0% 0% 0% 0% 0%
Phases are scheduled for Sept. 2021 through Jan. 2022
Phase is scheduled for May 2022
Phases are scheduled for August 2022 Phases are scheduled for June - July 2022
Building foundation complete. Storm Tie-ins complete.
100% 100%
Load bearing CMU complete.
Brick veneer complete. Curtain walls and CMP fascia's are ongoing.
85% 95% 85% 65% 70%
Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.
Wall paint and floor finishes ongoing in Classroom wings.
Substantial Completion 5/27/21.
0%
Status Comments
M A M J J A S O N D J F M
% Complete
Install and grade subbase, base paving where available. Ceilings, flooring and casework ongoing in the classroom wing. Exterior concrete paving and rough grading in parking area. Basement mechanical equipment piping is ongoing. Detailing remaining on flat roof, curtain walls installed.
95% 80% 75% 60% 20%
Issues in Progress
Finalizing wall graphic artwork, ordering material promptly will avoid delays for completion of interior finishes on specific walls.
Reviewing solutions to network connection in both New and existing building for Spring 2021.
Paid to Date (with 10% retained)
Remaining Material Allowance
Executed Change Orders
Original Material Allowance
$ $ $ $ $ $
2,913,301 1,374,684 2,605,874 15,759,275
$ $ $ $ $ $
(101,300)
$ $ $ $ $ $
113,400 56,375 53,150 255,625
$ $ $ $ $ $
89,756 43,536 88,337 51,819 9,350 282,798
- - - -
-
9,350
22,653,134
(101,300)
487,900
Aerial Shot
October 2020
Mr. Joseph S. Kovalchik, Superintendent Mr. Matthew Sawarynski, Business Administrator Mr. Jonathan Jenny, Director of Maintenance Mrs. Cassandra Herr, Principal
School Board David Gogel, President Charles Frantz, Vice President Dr. Michael Baird
John Becker James Chuss Charles Longacre Roy Maranki Robert Mentzell Ross Makary
Construction Manager D’Huy Engineering, Inc.
Project Architect KCBA Architects
Contractors Skepton Construction, Inc. General Construction
JBMMechanical, Inc. Mechanical Construction
Cyprium Solutions, Inc. Electrical Construction
Myco Mechanical, Inc. Plumbing Construction