New Lehigh Elementary School - July 2020
Work in Progress
Work In PRogress - Site
• Maintained E&S controls. • Continued installation of exterior concrete pads, frost walls, and sidewalks. • Continued installation of stormwater conveyance. • Began excavation of existing parking lot for expansion work. • Continued underground electrical duct bank for primary power.
Interior paint in classroom wing corridors.
Roof Installation