New Lehigh Elementary School - July 2020
Animated publication
Construction Manager
NEW LEHIGH ELEMENTARY SCHOOL Northampton Area School District
DEI Project No.022034 Monthly Progress Report No.15 July 2020
Work In Progress
• Phase 2B: Exterior veneer, roof structure and deck, interior wall construction, MEP equipment installation, interior finishes. • Start: April 15,2019 • Completion of Phase: June 15, 2021 Phase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.
• Continued sloped roof construction above the gymnasium, cafeteria, and main lobby. • Began installation of flat bituminous roofing system. • Continued exterior soffit and fascia framing. • Continued exterior veneer. • Continued installation of aluminum curtain wall assemblies. • Completed interior concrete slabs. • Continued installation of HVAC equipment and controls. • Began installation of terrazzo flooring in the 1st floor classroom wing. Work in Progress - Building
• Continued installation of branch wiring and system cabling. • Continued interior painting in the classroom wing. • Began installation of ceiling grid in the classroom wing. • Continued ceramic tile in 2nd floor gang bathrooms. • Completed roof drain and vent piping. • Began electrical piping in the gymnasium. • Continued non-load bearing walls in the Administration wing. • All roof curbs for HVAC equipment have been set.
Fascia and soffit framing around the flat roof areas.
Exterior aluminum curtain wall installation.
July 2020
Work in Progress
Work In PRogress - Site
• Maintained E&S controls. • Continued installation of exterior concrete pads, frost walls, and sidewalks. • Continued installation of stormwater conveyance. • Began excavation of existing parking lot for expansion work. • Continued underground electrical duct bank for primary power.
Interior paint in classroom wing corridors.
Roof Installation
Placement of terrazzo flooring in the classroom wing.
Gymnasium floor slab placement.
Grading of new parking lot.
July 2020
Renderings
Building Layout First Level
Building Layout Second Level
July 2020
School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034
2019
Overall Project Schedule Status
J‐F M‐A M‐J J‐A S‐O N‐D
Site Milestones 1S.1 ‐ 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT ‐ 4/30 1S.3 ‐ 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 ‐ 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 ‐ 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 ‐ 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 ‐ 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 ‐ 2BS.8: Topsoil install, painting of lots and drives 3S.1 ‐ 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 ‐ 3S.7: Abatement, installation of access roads and parking lots 4S.1 ‐ 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 ‐ 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 ‐ 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1‐1B.3 ‐ Prelim prep work, excavation & site, footings & foundations
1B.4 ‐ Load bearing CMU 1B.5 ‐ Exterior wall finishes
1B.6‐1B.8 ‐ Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9‐1B.12 ‐ Construction of interior walls, MEP rough‐ins and equipment installation 1B.13‐1B.16 ‐ Interior & floor finishes, equipment start‐up & commissioning, exterior finishes.
1B.17‐1B.19 ‐ Contractor cleanup and punchlist 1B.20‐1B.21 ‐ District cleanup, setup and move in
2020
J A S O N D
Current Phase and Schedule Status ‐ Site Phase 2B and Building Phase 1
1B.5‐1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 2AS.3‐2AS‐5: Parking lot tie‐ins to final grades, continue storm conveyance, make ready for school 1B.13‐1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3‐2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 1B.15‐1B.16: Equipment start‐up and commissioning, exterior finishes completed
Issues Resolved Reviewing traffic patterns for 20/21 School Year.
5,499,330 $ 1,248,759 $ 29,289,026 $ 4,080,000 $ 1,663,000 $ 118,026 $ 20,087,000 $ 3,341,000 $ Contract Amount
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.
Total Total Soft Costs: Current Remaining Project Contingency:
G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx
Report Submission Date: June 2020
Report Author: M. Evans
2020
2021
Status Comments
% Complete
J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D
95% 100% 100% 90%
Bus driveway base paving and curbing is completed. Parking lot work to be completed in Summer 2020 Utility work under parking lot to be completed in Summer 2020
60% 50% 60%
0% 0% 0% 0% 0% 0% 0% 0%
Phases are scheduled for Sept. 2021 through Jan. 2022
Phase is scheduled for May 2022 Phases are scheduled for June ‐ July 2022 Phases are scheduled for August 2022
Footings and foundations 100% complete. Storm tie‐in remaining.
95%
Insulation, brick veneer and curtainwall ongoing. Load bearing CMU to be completed June.
100%
80% 85% 70% 40% 50%
Roof structure complete. Shingle roof B/C complete and A roofing MEP roughs complete and equipment install is ongoing. Wall paint in 1st/2nd floor B/C underway, hard ceilings B/C ongoing.
Substantial Completion 5/16/21.
0%
2021
Status Comments
J F M A M J J A S O N D
% Complete
Exterior concrete curbing and sidewalk ongoing. Exterior wall finishes ongoing, equipment install ongoing. Exterior wall finishes, curtainwall and storefronts ongoing. Rough grading complete, curbing and paving ongoing Wall tile and paint ongoing, resilient flooring has begun.
70% 70% 60% 30% 25%
Issues in Progress
PennDOT conditional permit has been issued and ROW paperwork items are being finalized.
19,039,238 $ ‐ $ 1,895,808 $ 1,275,209 $ 2,298,119 $ 13,570,103 $ Paid to Date (with 10% retained)
Remaining Material Allowance 166,025 $ 48,063 $ 88,337 $ 51,819 $ 9,350 $ 363,593 $
(101,300) $ ‐ $ ‐ $ ‐ $ ‐ $ (101,300) $ Executed Change Orders
487,900 $ 9,350 $ 113,400 $ 56,375 $ 53,150 $ 255,625 $ Original Material Allowance
Aerial Shot
July 2020
Mr. Joseph S. Kovalchik, Superintendent Mr. Terry Leh, Business Administrator Mr. Jonathan Jenny, Director of Maintenance Mrs. Cassandra Herr, Principal School Board David Gogel, President Charles Frantz, Vice President Dr. Michael Baird
John Becker James Chuss Charles Longacre Roy Maranki Robert Mentzell Ross Makary
Construction Manager D’Huy Engineering, Inc. Project Architect KCBA Architects Contractors Skepton Construction, Inc. General Construction JBM Mechanical, Inc. Mechanical Construction Cyprium Solutions, Inc. Electrical Construction Myco Mechanical, Inc. Plumbing Construction