New Lehigh Elementary School - August 2020

Animated publication

Construction Manager

NEW LEHIGH ELEMENTARY SCHOOL Northampton Area School District

DEI Project No.022034 Monthly Progress Report No.16 August 2020

Work In Progress

•Phase 2B: Exterior veneer, roof structure and deck, interior wall construction, MEP equipment installation, interior finishes. •Start: April 15, 2019 •Completion of Phase: June 15, 2021 Phase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.

• Continued flat bituminous roofing system above the administration area and kitchen. • Completed exterior soffit framing. • Began installation of composite metal panels above window heads. • Completed exterior veneer. • Continued installation of exterior aluminum curtain wall assemblies. • Continued installation of HVAC equipment and controls. • Continued installation of terrazzo flooring in the 1st floor classroomwing. Work in Progress - Building

• Continued installation of branch wiring and system cabling. • Continued interior painting in the classroomwing. • Continued installation of ceiling grid in the classroomwing. • Completed installation of ceramic wall tile in gang bathrooms. • Began ceramic wall tile installation in single bathrooms and janitor closets. • Completed non-load bearing walls in the administration area. • Completed above ceiling MEP rough ins in the gymnasium.

Brick veneer is complete, and soffits and fascia have continued.

Installation of epoxy terrazzo in the classroomwing.

August 2020

Work in Progress

• Completed a portion of the parking lot expansion and maintained bus drop off loop prior to the start of the 20-21 school year. • Continued installation of exterior concrete pads, frost walls, and sidewalks. • Completed installation of concrete curbing in portions of the new parking lot. Work In Progress - Site

• Completed a portion of the parking lot expansion and maintained bus drop off loop prior to the start of the 20-21 school year. • Began installation of exterior site lights. • Began installation of conduit piping for septic pumps. • Received fire water tank and pump house for installation. • Completed underground electrical conduit installation for primary power. •Maintained E&S controls.

• Continued installation of stormwater conveyance.

Expansion of parking lot for 20-21 school year.

Installation of conduit for primary power.

Ceiling grid installation in first floor corridors and classrooms.

Completion of a portion of the flat bituminous roofing system.

Aluminum storefronts and curtain walls are completed at the main entrance

August 2020

Renderings

Building Layout First Level

Building Layout Second Level

August 2020

School District:  Northampton Area School District Project Name:  New Lehigh Elementary School Project Number:  022034

2019

Overall Project Schedule Status

J‐F M‐A M‐J J‐A S‐O N‐D

Site Milestones 1S.1 ‐ 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT ‐ 4/30 1S.3 ‐ 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of  Powerlines 1S.7: Demolition of Residence 1S.8 ‐ 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 ‐ 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 ‐ 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 ‐ 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 ‐ 2BS.8: Topsoil install, painting of lots and drives 3S.1 ‐ 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 ‐ 3S.7: Abatement, installation of access roads and parking lots 4S.1 ‐ 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 ‐ 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 ‐ 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1‐1B.3 ‐ Prelim prep work, excavation & site, footings & foundations

1B.4 ‐ Load bearing CMU 1B.5 ‐ Exterior wall finishes

1B.6‐1B.8 ‐ Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9‐1B.12 ‐ Construction of interior walls, MEP rough‐ins and equipment installation  1B.13‐1B.16 ‐ Interior & floor finishes, equipment start‐up & commissioning, exterior finishes.

1B.17‐1B.19 ‐ Contractor cleanup and punchlist 1B.20‐1B.21 ‐ District cleanup, setup and move in

2020

202

A S O N D J

Current Phase and Schedule Status ‐ Site Phase 2B and Building Phase 1

1B.5‐1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 2AS.3‐2AS‐5: Parking lot tie‐ins to final grades, continue storm conveyance, make ready for school 1B.13‐1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3‐2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 1B.15‐1B.16: Equipment start‐up and commissioning, exterior finishes completed

Issues Resolved Traffic patterns resolved for 20‐21 school year. 

HOP ROW plans and paperwork finalized and accepted by PennDOT.

20,087,000 $               3,341,000 $                  Contract Amount 1,663,000 $                  118,026 $                     5,499,330 $                   1,248,759 $                   29,289,026 $               4,080,000 $                 

Contract General Contractor: Skepton Construction, Inc.  Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.

Total Total Soft Costs: Current Remaining Project Contingency:

G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx

Report Submission Date: August 2020

Report Author: M. Evans

2020

2021

Status Comments

% Complete

J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D

100% 100% 100% 90% 95% 100%

Parking lot utility work completed.

Bus driveway base paving and curbing is completed. Parking lot base tie‐in complete. Landscaping behind curbs ongoing. Finalized new parking and service areas. Secure site for school. 

75% 25%

0% 0% 0% 0% 0% 0% 0%

Phases are scheduled for Sept. 2021 through Jan. 2022

Phases are scheduled for June ‐ July 2022 Phase is scheduled for May 2022 Phases are scheduled for August 2022

Footings and foundations 100% complete. Storm tie‐in remaining.

95%

Load bearing CMU complete.

100%

MEP roughs complete and equipment install is ongoing.  Wall paint in 1st/2nd floor B/C underway, ceilings are ongoing. Brick veneer complete. Soffits, fascia and curtainwalls ongoing. Roof structure complete. Roof detailing ongoing. 

75% 45% 50% 90% 80%

Substantial Completion 5/16/21.

0%

21

Status Comments

F M A M J J A S O N D J

% Complete

Exterior concrete curbing and sidewalk ongoing. Exterior wall finishes ongoing, equipment install ongoing.  Main portion of flat roof complete. Flashing and details remaining. Parking lot tie in‐complete. Wall tile and paint ongoing. Terrazzo is ongoing.

80% 100%

65% 45% 30%

Issues in Progress

14,194,091 $                         2,394,329 $                           Paid to Date (with 10%  retained) 2,110,076 $                           1,293,069 $                           ‐ $                                        19,991,565 $                        

Remaining Material Allowance 136,714 $                                                   48,063 $                                                      88,337 $                                                      51,819 $                                                      9,350 $                                                        334,282 $                                                  

(101,300) $                              ‐ $                                        Executed Change Orders ‐ $                                        ‐ $                                        ‐ $                                        (101,300) $                             

255,625 $                                    53,150 $                                      Original Material Allowance 113,400 $                                    56,375 $                                      9,350 $                                        487,900 $                                   

Aerial Shot

August 2020

Mr. Joseph S. Kovalchik, Superintendent Mr. Matthew Sawarynski, Business Administrator Mr. Jonathan Jenny, Director of Maintenance Mrs. Cassandra Herr, Principal

School Board David Gogel, President Charles Frantz, Vice President Dr. Michael Baird

John Becker James Chuss Charles Longacre Roy Maranki Robert Mentzell Ross Makary

Construction Manager D’Huy Engineering, Inc.

Project Architect KCBA Architects

Contractors Skepton Construction, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Cyprium Solutions, Inc. Electrical Construction

Myco Mechanical, Inc. Plumbing Construction