New Garden Elementary School

RENOVATIONS / ADDITIONS

NEW CONSTRUCTION

Advantages

Disadvantages

Advantages

Disadvantages

Lower Construction Costs

Challenges with ADA Compliance & Accessibility Higher maintenance costs of concealed plumbing and electrical infrastructure Greater risk of unforeseen conditions discovered during construction Longer (phased) construction duration Existing construction limits technology integration Constraints on learning space configurations working

Better use of space & design opportunity

Higher Construction Cost

Maintaining existing history & character

Maintenance Savings

Demolition of existing structure costs

Construction & Materials warranties

Shorter construction duration with less disturbance programs Ability to Green design

Increased energy efficiency

Increased safety & security Integrated technology Improve Civic Presence

Kennett Consolidation School District Construction Cost Worksheet 750 PDE Capacity School (Greenwood and New Garden) | 61,950 Architectural Area x 1.68 sq ft = 104,100 Base Cost Per School Summary of Construction Costs

Site Development

$ 4,500,000 $500,000 $500,000 $5,500,000 $4,500,000 $1,500,000

Demolition

Remediation

Mechanical Contractor Electrical Contractor Plumbing Contractor

Fire Protection

$700,000

GREENWOOD & NEW GARDEN ELEMENTARY SCHOOLS Kennett Consolidated School District eneral Contractor Per school Construction Sub-Total

$25,300,000 $43,000,000

PROJECT TIMELINE - SIMULTANEOUS OPENING

21

2022

2023

2024

2025

2026

2027

2028

PHASE

DURATION

N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

November 2021 - May 2022

District-Wide Feasibility Study Update GREENWOOD & NEW GARDEN DESIGN PHASES Programming/Schematic Design

June 2022 - October 2022 October 2022 - January 2023

Design Development

NEW GARDEN ELEMENTARY Construction Documents Bidding/Award of Contracts

January 2023 - September 2023 October 2023 - December 2023 January 2024 - December 2025

24 MONTHS

New School Construction Demolition & Site Work

JOINT OPENING

July 2026 - June 2027

GREENWOOD ELEMENTARY Construction Documents Bidding/Award of Contracts

October 2023 - April 2024 May 2024 - July 2024 August 2024 - July 2026 July 2026 - June 2027

24 MONTHS

New School Construction Demolition & Site Work

Made with FlippingBook Digital Publishing Software