New Fire Station #3 and New Fire Station #73 for Northampton Township

Station #3

Northampton Township Fire Station #3 Project Number: 721001

2022

Overall Project Schedule Status

J-F M-A M-J J-A S-O N-D J-F

Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B3.1 to B3.4 - Place foundations. Complete under slab MEP rough-in. Complete slab on grade and cure time. B3.5 to B3.7 - Erect structural steel. Complete masonry walls. Complete roof (building to be watertight). B3.8 to B3.12 - Complete interior CMU walls, metal studs. Complete in-wall MEP rough-ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough-ins. B3.13 to B3.16 - Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B3.17 to B3.20 - Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B3.21 to B3.23 - Complete fire alarm and security system. MEP start-up.. Complete elevator inspection. B3.24 to B3.27 - Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B3.28 to B3.30 - Substantial completion, Final completion. Owner furniture, fixtures and equipment move-in and occupy. S3.1 to S3.6 - NTP,process shop dwgs/submittal/begin procurement Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence,protect communication tower, install staging area,construction entrance,construction trailers,temp. power. EC provide temp overhead connections. S3.7 to S3.11 - Demo existing fire station incl footings, foundations. Provide protection for cell town bldg. Fill void from basement. Route new utilities for tower. Inst. Stormwater basin and storm sewer piping. S3.12 to S3.15 - Prepare bldg pad, inst. Undergrnd electric, gas to bldg. pad. Inst. San. Sewer/water piping and connect to street S3.16 to S3.18 - Complete rough grading, inst. ret. walls, ext. light bases, post, lights. Inst. concrete curbs/sidewalks incl. work along Township Road. S3.19 to S3.21 - Inst. stone base, base course paving for const. access including along Township Road. Inst. final pave and line striping. Complete final grading, seeding, landscaping. Current Phase and Schedule Status

Phas

F M A M J J A

Issues Resolved

Pa

Contract General Contractor: E. R. Stuebner, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Philips Brothers Electrial Contractors, Inc. Plumbing Contractor: JBM Mechanical, Inc.

Contract Amount

$ $ $ $ $

27,983,000 2,100,000 3,615,000 3,021,000 19,247,000

$ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency

Made with FlippingBook Ebook Creator