New Fire Station #3 and New Fire Station #73 for Northampton Township

Animated publication

NEW FIRE STATION #3 AND NEW FIRE STATION #73 Northampton Township DEI Project No. 721001 Monthly Progress Report No. 1 April, 2022

NEW FIRE STATION #3 AND NEW FIRE STATION #73

SITEWORK FIRE STATION #3 Phase Sitework: Demolition of existing fire station Start: March 4, 2022 Completion of Phase: April 13, 2023

SITEWORK FIRE STATION #73 Phase Sitework: Demolition of existing fire station Start: May 4, 2022 Completion of Phase: June 16, 2023

April 2022

NEW FIRE STATION #3 AND NEW FIRE STATION #73

WORK COMPLETED STATION #3

• Held construction kick-off meetings with construction team and Bucks County Conservation District • Processing of shop drawings and submittals • Begin procurement of long lead items • Begin 3D modeling and coordination drawings • Establish weekly superintendent construction meetings • Completed owner move out • Install construction entrances and fencing • Establish and maintain E&S controls • Scan and location of all existing underground utilities to existing building and cell site • Establish construction staging area • Placement of construction trailers and installation of temporary power • Installation of protection of communications tower and associated facilities • Demolition of existing building structure and foundations • Separate and process materials from building demolition • Begin site clearing • Begin coordinating relocation of cell site existing underground utilities

Station #3 Structural Demolition

Station #3 Structural Demolition

Station #3 Demo

WORK COMPLETED STATION #73

• Processing of shop drawings and submittals • Begin procurement of long lead items • Establish weekly superintendent construction meetings • Install construction entrances and fencing

• Establish and maintain E&S controls • Placement of construction trailers

• Demolition of existing building structure and foundations • Separate and process materials from building demolition • Preparation of building pad

Station #73 Demo and Building Pad Preparation

Station #73 Structural Demolition

April 2022

NEW FIRE STATION #3 AND NEW FIRE STATION #73

Building Layout: Station #3

Building Layout: Station #73

April 2022

Station #3

Northampton Township Fire Station #3 Project Number: 721001

2022

Overall Project Schedule Status

J-F M-A M-J J-A S-O N-D J-F

Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B3.1 to B3.4 - Place foundations. Complete under slab MEP rough-in. Complete slab on grade and cure time. B3.5 to B3.7 - Erect structural steel. Complete masonry walls. Complete roof (building to be watertight). B3.8 to B3.12 - Complete interior CMU walls, metal studs. Complete in-wall MEP rough-ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough-ins. B3.13 to B3.16 - Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B3.17 to B3.20 - Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B3.21 to B3.23 - Complete fire alarm and security system. MEP start-up.. Complete elevator inspection. B3.24 to B3.27 - Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B3.28 to B3.30 - Substantial completion, Final completion. Owner furniture, fixtures and equipment move-in and occupy. S3.1 to S3.6 - NTP,process shop dwgs/submittal/begin procurement Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence,protect communication tower, install staging area,construction entrance,construction trailers,temp. power. EC provide temp overhead connections. S3.7 to S3.11 - Demo existing fire station incl footings, foundations. Provide protection for cell town bldg. Fill void from basement. Route new utilities for tower. Inst. Stormwater basin and storm sewer piping. S3.12 to S3.15 - Prepare bldg pad, inst. Undergrnd electric, gas to bldg. pad. Inst. San. Sewer/water piping and connect to street S3.16 to S3.18 - Complete rough grading, inst. ret. walls, ext. light bases, post, lights. Inst. concrete curbs/sidewalks incl. work along Township Road. S3.19 to S3.21 - Inst. stone base, base course paving for const. access including along Township Road. Inst. final pave and line striping. Complete final grading, seeding, landscaping. Current Phase and Schedule Status

Phas

F M A M J J A

Issues Resolved

Pa

Contract General Contractor: E. R. Stuebner, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Philips Brothers Electrial Contractors, Inc. Plumbing Contractor: JBM Mechanical, Inc.

Contract Amount

$ $ $ $ $

27,983,000 2,100,000 3,615,000 3,021,000 19,247,000

$ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency

Report Submission Date:

05/06/22

Report Author: Colin Case

2023

Status Comments

M-A M-J J-A S-O N-D

% Complete

In progress: Building demolition completed July 2022 thru June 2023

July 2022 thru August 2023

September 2022 thru October 2022

November 2022 thru December 2022

January 2023 thru February 2023

February 2023 thru March 2023

March 2023 thru April 2023

April 2023 thru June 2023

June 2023

se Sitework 2022 - 2023

Status Comments

S O N D J F M A

% Complete

Completed

Demolition, Temporary fencing, power, construction trailer an

Building pad construction underway.

Identifying and tracing all cell tower utilties. Issues in Progress

Remaining Material Allowance

aid to Date (with 10% retained)

Original Material Allowance

Executed Change Orders

822,753 155,934

$ $ $ $ $

- - - - -

$ $ $ $ $

909,087.40 76,465.00 131,682.40 88,540.00 612,400.00

$ $ $ $ $

612,400.00 95,540.00 131,682.40 76,465.00 916,087.40

-

91,832

1,070,518

Printed 5/5/2022 1 of 2

Station #73

Northampton Township Fire Station #73 Project Number: 721001

2022

Overall Project Schedule Status

J-F M-A M-J J-A S-O N-D J-F

Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B1 to B4 - Place foundations. Complete under slab MEP rough-in. Complete slab on grade and cure time. B5 to B7 - Erect structural steel. Complete exterior masonry walls. Complete roof (building to be watertight). B8 to B12 - Complete interior CMU walls, metal studs. Complete in-wall MEP rough-ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough-ins. B13 to B16 - Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B17 to B20 - Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B21 to B24 - Complete fire alarm and security system. MEP start-up. Relocated offices from trailers to inside bldg. Complete elevator inspection. B25 to B28 - Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B29 to B31 - Substantial completion, Final completion. Owner furniture, fixtures and equipment move-in and occupy. S1 to S4 - NTP,process shop dwgs/submittal/begin procurement. Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence, protect Verizon building. S5 to S9 - Demo existing fire station incl footings, foundations and existing underground fuel oil tank. Install staging area, construction entrance, construction trailers, temporary, power, site lighting and communication from existing utilities. EC provide temporary overhead connections. Route new utilities for Verizon bldg. Install stormwater basin and connect to street and storm sewer piping to basin. S10 to S14 - Prepare bldg.pad, install underground electric and gas to bldg.pad. Install sanitary piping. Sewer piping connect to street pipe. Complete rough grading, install retaining walls. S15 to S20 - Remove construction trailers. Inst. ext. light bases, posts, lights. Inst. conc. curbs, stone base, base course paving for const. access. Inst. final paving and line striping. Complete final grading, seeding and landscaping. Current Phase and Schedule Status

Phas

F M A M J J A

Issues Resolved Unsuitable soils are being removed and replaced with engineered fill.

Pa

Contract General Contractor: E. R. Stuebner, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Philips Brothers Electrial Contractors, Inc. Plumbing Contractor: JBM Mechanical, Inc.

Contract Amount

$ $ $ $ $

19,247,000 3,021,000 3,615,000 2,100,000 27,983,000

$ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency

Report Submission Date:

05/06/22

Report Author: Colin Case

2023

Status Comments

M-A M-J J-A S-O N-D

% Complete

10% In progress: Building demolition completed

July 2022 thru July 2023

July 2022 thru August 2023

September 2022 thru October 2022

November 2022 thru December 2022

January 2023 thru February 2023

February 2023 thru March 2023

March 2023 thru April 2023

April 2023 thru June 2023

June 2023 thru July 2023

se Sitework 2022 - 2023

Status Comments

S O N D J F M A M J J

% Complete

100% Completed

Demolition, Temporary fencing, power, construction trailer and staging areas completed.

80%

Building pad construction underway.

Issues in Progress Unsuitable soils discovered below the existing building.

Remaining Material Allowance

aid to Date (with 10% retained)

Original Material Allowance

Executed Change Orders

822,753 155,934

$ $ $ $ $

- - - - -

$ $ $ $ $

612,400.00 88,540.00 131,682.40 76,465.00 909,087.40

$ $ $ $ $

612,400.00 95,540.00 131,682.40 76,465.00 916,087.40

-

91,832

1,070,518

Printed 5/5/2022 2 of 2