New Central Emergency Services Facility -

New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.18, P1.20,

Erect Structural Steel (09/30/21) Complete interior walls (10/15/21) Complete and cure Slab on Grade (10/13/21) Ongoing: P1.19, P1.21 – P1.25 Complete Roof – Roof Watertight (10/26/21) Complete MEP System Placement (12/15/21) Complete Painting of Walls (11/29/21)

Site Construction Progress Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete base and binder courses on all asphalt paving.

• Continue light pole base installation. • Reseed site around sediment basin.

Building Construction Progress

• Complete masonry wall installation and MEP in-wall rough-ins nearing completion. • Complete steel erection and detailing and conduct final steel inspection. • Complete exterior masonry wall installation. • Continue mechanical hanger, duct, and pipe rough-in. • Continue rough-in including gas piping. • Continue electrical branch wiring. • Exterior metal framing and sheathing nearing completion. • Continue spray foam insulation. • Complete installation of sloped roof insulation, nail board, and vapor barrier. • Complete installation of insulation and base-ply of central hot-applied roof. • Roof is nowweathertight.