New Central Emergency Services Facility Upper Providence Township

DEI Project No.720001 Monthly Progress Report No.07 October 2021

New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.18, P1.20,

Erect Structural Steel (09/30/21) Complete interior walls (10/15/21) Complete and cure Slab on Grade (10/13/21) Ongoing: P1.19, P1.21 – P1.25 Complete Roof – Roof Watertight (10/26/21) Complete MEP System Placement (12/15/21) Complete Painting of Walls (11/29/21)

Site Construction Progress Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete base and binder courses on all asphalt paving.

• Continue light pole base installation. • Reseed site around sediment basin.

Building Construction Progress

• Complete masonry wall installation and MEP in-wall rough-ins nearing completion. • Complete steel erection and detailing and conduct final steel inspection. • Complete exterior masonry wall installation. • Continue mechanical hanger, duct, and pipe rough-in. • Continue rough-in including gas piping. • Continue electrical branch wiring. • Exterior metal framing and sheathing nearing completion. • Continue spray foam insulation. • Complete installation of sloped roof insulation, nail board, and vapor barrier. • Complete installation of insulation and base-ply of central hot-applied roof. • Roof is nowweathertight.

y

Central roof watertight.

Block filler and duct insulation ongoing.

October 2021

New Central Emergency Services Facility

Projected Progress for Nov. 2021

• Complete duct insulation. • Complete overhead MEP rough-in in all building areas. • Continue interior block filler and painting. • Complete spray-foam insulation. • Begin installation of exterior brick veneer and stone. • Complete exterior framing and sheathing. • Begin setting mechanical VAV units. • Begin installation of windows. • Place concrete patio, metal pan stairs, and front and rear aprons. • Complete Plymavent System. • Begin installation of roof and exterior wall metal panels. • Continue interior framing and drywall installation. • Install apparatus bay doors.

Main electrical panel installation ongoing.

Exterior sheathing nearing completion.

y

Apparatus bay spray foam insulation installation ongoing.

Light pole and bases installation nearing completion.

October 2021

Building Layout

Aerial view of building and material laydown area (October 2021).

Site Overview (October 2021).

Building Floor Plan

Building Site Plan

October 2021

Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001 Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001 Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals Overall Project Schedule Status Overall Project Schedule Status

2021

J

F M A M J

J

2021

P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones 3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance nd Fence, New Util ties installation 1 ‐ Installation of Site Lighting Bases and Lights 2 ‐ Curbing and Stone base fo Parking Lots and Sidewalk installation 43 44 Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving .54‐P1.55 ‐ Project Substantial and Final Completion Current Phase and Schedule Status P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems P1.24 ‐ Energize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid and Complete Hard Ceilings P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems P1.24 ‐ En rgize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid a d C mplete H Ceilings Current Phas and Schedule Status Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Issues Resolved Work with Vision Mechanical on resolving sprinkler shop darwings and calculations. Coordinate with Lobar on roof nail board and stone veneer procurement. Coordinate the FF&E process with GKO and the Township. Complete building low voltage, security, and access control design with GKO and CEI. Issues Resolved Work with Vision Mechanical on resolving sprinkler shop darwings and calculations. Coordinate with Lobar on roof nail board and stone veneer procurement. Coordinate the FF&E process with GKO and the Township. Complete building low voltage, security, and access control design with GKO and CEI.

J

F M A M J

J

J F M A M J J

J F M A M J J

P

Contract Amount

$ $ $ $ $

7,462,000 1,123,000 1,212,400 7,462,000 1,123,000 1,212,400 10,719,597 922,197

$ $ $ $ $

Contract Amount

$ $ $ $ $

$ $ $ $ $

Total Total Soft Costs: Current Remaining Project Contingency Total Total Soft Costs: Current Remaining Project Contingency

922,197

10,719,597

Other Discussion

Other Discussion

Report Submission Date: November 2021

Report Author: Michael DePodwin Report Submission Date: November 2021

1

2022

A S O N

D J

F M A M J

% Complete

Status Comments

Report Author: Michael DePodwin

Resubmittals nearing completion

1

2022

99%

Slab on Grade and Structural Steel complete. Exterior walls complete. Roof weathertight. Interior block wall complete. MEP rough‐in ongoing Interior block filler ongoing. Status Comments Slab on Grade and Structural Steel complete. Exterior walls complete. Roof weathertight. Interior block wall complete. MEP rough‐in ongoing Interior block filler ongoing. Resubmittals nearing completion All light pole bases installed. Light pole installation ongoing Complete Stabilization of site complete Base and binder paving courses complete. Fence to be completed All light pole bases installed. Light pole installation ongoing Complete Stabilization of site complete Base and binder paving courses complete. Fence to be completed

0% 0% 9 1 0% 25% 90% 100% 10% 0% 0 100% 90% 90% 100% 90% 90% 99% 10% 0% 0% 99% 25% 60% 99

A S O N

D J

F M A M J

% Complete

Phase 1 2021

60%

Status Comments

A S O N D J F M A M J

% Complete 0%

100% 100% 0%

Complete Complete

Phase 1 2021

Roof weathertight. Metal roof and cap sheet outstanding. Complete All system installation ongoing. Roof weathertight. Metal roof and cap sheet outstanding. Complete All system installation ongoing. Status Comments

80%

A S O N D J F M A M J

% Complete

100%

95% Nearing completion 80% 10% Block filler underway 95% Nearing completion 80% 10% Block filler underway 80% 100% 100% Complete Complete 100% 0%

Issues in Progress

Review cost proposal from ETI regarding low voltage, security, and access control changes. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Ensure site hours, noise, and lighting are compliant with Township ordinances. Continue to track equipment and material procurement to ensure critical path remain on schedule. 0% Issues in Progress Review cost proposal from ETI regarding low voltage, security, and access control changes. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Ensure site hours, noise, and lighting are compliant with Township ordinances. Continue to track equipment and material procurement to ensure critical path remain on schedule. Executed Change Orders Original Material Allowance

Paid to Date (with 10% retained)

Remaining Material Allowance

4,818,025

$ $ $ $ $

‐ ‐ ‐ ‐

$ $ $ $ $

209,365 47,807 94,098 37,920 209,365 389,190 47,807 389,190 37,920 94,098

$ $ $ $ $

184,489 47,807 98,883 64,622 395,800 184,489 47,807 98,883 64,622 395,800

482,268 533,674 476,034 4,818,025 Paid to Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $

‐ ‐ ‐ ‐

$ $ $ $ $

$ $ $ $ $

6,310,001 482,268

533,674 476,034

6,310,001

87% 0% Submittals 0% Submittals

98% Requests for Information 0% Requests for Information

0%

Approved Rejected Voided Overdue Approv d Rejected Voided Overdue

0%

13%

Complete Outstanding Voided Overdue Complete Outstanding Voided Overdue

2%

0%

0%

13%

0%

2%

87%

98%

Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services

Board of Supervisors Bill Starling – Chair Laurie Higgins – Vice Chair

Helene Calci John Pearson Albert Vagnozzi

Construction Manager D’huy Engineering, Inc.

Project Architect Gko Architects, Llc

Civil Engineer Gilmore & Associates, Inc.

Contractors Lobar, Inc. General Construction

Tri-County Mechanical, Inc. Mechanical Construction

Electri-Tech, Inc. Electrical Construction

Vision Mechanical, Inc. Plumbing Construction