New Central Emergency Services Facility -Upper Providence Township
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
20
Overall Project Schedule Status
J
F M A M J
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals
P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping
P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion
Current Phase and Schedule Status
J F M A M J
P1.14 ‐ Complete under slab MEP piping and conduit P1.15 ‐ Complete Slab on Grade P1.16 ‐ Slab on Grade Curing Time P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems
Issues Resolved Confirm installation detail and construction sequence of the apparatus bay trench drains. Coordinate with Lobar on roof nail board and stone veneer procurement. Coordinate the FF&E process with GKO and the Township. GKO confirmed building efficiency through a COMCheck stemming from perimeter insulation question.
Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.
Contract Amount
$ $ $ $ $
7,462,000 1,123,000 1,212,400
922,197
Total Total Soft Costs: Current Remaining Project Contingency
10,719,597
Other Discussion
Made with FlippingBook - Online catalogs