New Central Emergency Services Facility -Upper Providence Township

New Central Emergency Services Facility

Projected Progress for OCt. 2021

• Complete interior masonry wall installation and in-wall electrical rough-ins. • Complete exterior masonry wall installation. • Receive final steel inspection sign off. • Complete installation of sloped metal roof and 2-ply membrane flat roof.

• Complete mechanical duct and pipe hanger installation. • Continue overhead MEP rough-in in all building areas. • Begin interior painting. • Begin spray-foam insulation. • Begin installation of exterior brick veneer and stone. • Complete exterior framing and sheathing.

Concrete slab preparation completed in apparatus bay.

Base and binder paving courses complete.