New Central Emergency Services Facility - Upper Providence Township

Animated publication

Construction Manager

New Central Emergency Services Facility Upper Providence Township

DEI Project No.720001 Monthly Progress Report No.04 July 2021

New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.10, P1.12, P1.13 Complete building pad (05/28/21) Place building foundations (06/11/21) Install underground water & sanitary (05/11/21) Ongoing: P1.14 – P1.18 Complete under slab MEP (07/02/21) Complete and cure Slab on Grade (07/16/21) Erect Structural Steel (07/30/21) Complete Exterior MasonryWalls (08/17/21)

Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete sediment basin and stabilize the southern half of the site. • Begin Belgian block and concrete curb installation. • Begin roadway subgrade installation. • Complete underground electric and fiber optic duct bank installation. • Begin underground conduit installation for site lighting. Site Construction Progress • Continue under slab MEP installation. • Complete interior masonry wall installation at Area C. • Continue interior masonry wall installation at Areas A and B while coordinating with MEP for in-wall rough-ins. • Prep & pour slab on grade Area A. • Continue structural steel erection and detailing. • Begin installation of metal roof decking. • Place pre-cast concrete planks. • Begin exterior masonry wall installation starting at the main entrance. Building Construction Progress

y

Pre-cast concrete plank placement.

Ongoing interior masonry wall installation.

July 2021

New Central Emergency Services Facility

Projected Progress for August 2021

• Continue interior masonry wall installation and in-wall electrical rough-ins. • Continue exterior masonry wall installation. • Complete under slab MEP installation including the interior section of the radiant heat system and apparatus bay trench drains.

• Complete erection and detailing of structural steel. • Prep and pour mezzanine concrete slab on metal deck. • Complete concrete curb installation and road subgrade. • Complete underground conduit for site lighting. • Install temporary power at the building pad.

Ongoing curb installation.

Stabilization of sediment basin.

y

Steel detailing and exterior masonry wall installation is ongoing.

Apparatus bay steel and acoustic decking.

July 2021

Building Layout

Aerial view of building superstructure and material laydown area (July 2021).

Site Overview (July 2021).

July 2021

Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001

20

Overall Project Schedule Status

J

F M A M J

Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals

P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping

P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion

Current Phase and Schedule Status

J F M A M J

P1.4 ‐ Establish temporary power, site lighting, and communications from existing utilities. P1.6 ‐ Install basin and perform site rough grading P1.8‐P1.11 ‐ Install MEP to building pad P1.13 ‐ Place building foundations P1.14 ‐ Complete under slab MEP piping and conduit

P1.15 ‐ Complete Slab on Grade P1.16 ‐ Slab on Grade Curing Time P1.17 ‐ Erect Structural Steel

Issues Resolved Confirm installation detail and construction sequence of the apparatus bay trench drains.

Confirmation of Belgian block curb detail, width of main loop road entrance, roof drain cleanout product. Coordinate the FF&E process with GKO and the Township

Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.

Contract Amount

$ $ $ $ $

1,212,400 1,123,000 7,462,000

922,197

Total Total Soft Costs: Current Remaining Project Contingency

10,719,597

Other Discussion

Report Submission Date: July 2021

Report Author: Michael DePodwin

021

2022

J

A S O N

D J

F M A M J

% Complete

Status Comments

Resubmittals nearing completion

95% 85% 15% 20%

Slab on Grade and Structural Steel Ongoing Exterior block wall isntallation ongoing Interior block wall and MEP rough‐in ongoing

0% 0% 0%

Fence to be completed

50% 75% 99%

Underground rough‐in ongoing Curbs complete, stone base ongoing

0% 0% 0% 0%

Phase 1 2021

Status Comments

J A S O N D J F M A M J

% Complete

100%

Complete

100% Complete

90%

All utilities have been terminated building side save for gas.

100% Complete

50% Area B slab on grade complete 75% 50% Area A slab on grade ongoing.

MEP rough‐in continuing in apparatus bay and mechanical room

90% Erection and detailing nearing completion.

Issues in Progress

Work with Vision Mechanical on resolving sprinkler shops drawings and calculations.

Complete a building low voltage, security, and access control design with GKO and CEI. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. GKO to confirm building efficiency through a COMCheck stemming from perimeter insulation question.

Paid to Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $

2,956,059

$ $ $ $ $

‐ ‐ ‐ ‐ ‐

$ $ $ $ $

389,190 94,098 37,920 47,807 209,365

$ $ $ $ $

189,198 47,807 92,910 64,622 394,537

318,473 310,238 129,598

3,714,369

1% Submittals

Requests for Information

0%

Approved Rejected Voided Overdue

2% 0%

12%

0%

Complete Outstanding Voided

87%

98%

Printed 8/12/2021

Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services

Board of Supervisors Bill Starling – Chair Laurie Higgins – Vice Chair

Helene Calci John Pearson Albert Vagnozzi

Construction Manager D’huy Engineering, Inc.

Project Architect Gko Architects, Llc

Civil Engineer Gilmore & Associates, Inc.

Contractors Lobar, Inc. General Construction

Tri-County Mechanical, Inc. Mechanical Construction

Electri-Tech, Inc. Electrical Construction

Vision Mechanical, Inc. Plumbing Construction