New Central Emergency Services Facility - Upper Providence Township
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
Overall Project Schedule Status
J
F M A M
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals
P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement
P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP C i i i P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping
P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion
Current Phase and Schedule Status
J F M A M
P1.4 ‐ Establish temporary power, site lighting, and communications from existing utilities. P1.5 ‐ Install Temporary Electric for Construction Activities P1.6 ‐ Install basin and perform site rough grading
P1.7 ‐ Prepare building pad for foundations P1.8‐P1.11 ‐ Install MEP to building pad P1.12 ‐ Install building pad subgrade and complete building pad P1.13 ‐ Place building foundations P1.14 ‐ Complete under slab MEP piping and conduit
Issues Resolved Coordinate with PECO on energizing construction trailer temporary power pole. Confirm with Gilmore on new grading of merger pit and southwest corner of the sediment basin. Confirm new construction sequence and water pumping detail of the sediment basin proposed by Lobar, with Gilmore and MCCD.
Change construction detail of East Training O.A.C Room wall from decorative CMU to GWB on metal studs.
Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.
Contract Amount
$ $ $ $ $
7,462,000 1,123,000 1,212,400
922,197
Total Total Soft Costs: Current Remaining Project Contingency
10,719,597
Other Discussion
Made with FlippingBook flipbook maker