New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.8, P1.12, P1.13 Complete building pad (05/28/21) Place building foundations (06/11/21) Ongoing: P1.8 – P1.11, P1.14 Install underground electric (05/04/21) Install underground water & sanitary (05/11/21)

Install underground gas (05/18/21) Complete under slab MEP (07/02/21)

Site Construction Progress Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete temporary electric to trailers. • Continue grading of site using the Township stockpile at the west end of the site. • Complete excavation and installation of storm structures at the sediment basin. • Continue site sewer and storm installation. • Begin installation of the water line from the meter pit to the building. • Begin underground electric duct bank installation.

Building Construction Progress

• Continue the BIM 3D modeling coordination drawing process. • Complete placement of concrete foundation walls and footings. • Complete masonry foundation walls and MEP foundation sleeves. • Complete foundation damp-proofing and insulation. • Complete structural backfilling of foundation walls. • Begin under slab MEP installation. • Begin preparing the building to receive concrete slab on grade.