New Central Emergency Services Facility - March & April Monthly Report
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
Overall Project Schedule Status
J
F M A M
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals
P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement
P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping
P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion
Current Phase and Schedule Status
J F M A M
P.3 ‐ Install Temporary E&S Protection and Temporary Construction Fence P1.4 ‐ Perform tree, shrub and vegetation removal. Install Staging area and construction entrance P1.4 ‐ Establish temporary power, site lighting, and communications from existing utilities. P1.5 ‐ Install Temporary Electric for Construction Activities P1.6 ‐ Install basin and perform site rough grading P1.7 ‐ Prepare building pad for foundations P1.8 ‐ P1.11 ‐ Install underground electric, sanitary, water, and gas to building pad P1.13 ‐ Place building foundations Issues Resolved Note limit of disturbance in relation to neighboring property. Monitor contractor parking to stay within construction fence and across Black Rock Rd. Safe removal of mulch pile.
Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.
Contract Amount
$ $ $ $ $
7,462,000 1,123,000 1,212,400
922,197
Total Total Soft Costs: Current Remaining Project Contingency
10,719,597
Other Discussion