New Central Emergency Services Facility

Animated publication

Construction Manager

New Central Emergency Services Facility Upper Providence Township

DEI Project No.720001 Monthly Progress Report No.03 June 2021

New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.10, P1.12, P1.13 Complete building pad (05/28/21) Place building foundations (06/11/21) Install underground water & sanitary (05/11/21) Ongoing: P1.14 – P1.18 Complete under slab MEP (07/02/21) Complete and cure Slab on Grade (07/16/21) Erect Structural Steel (07/30/21) Complete Exterior MasonryWalls (08/17/21)

Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Install new PECO power pole at northeast corner of the site. • Complete grading of site using the Township stockpile at the west end of the site. • Complete site sewer and storm installation. • Complete site water line installation. • Successful pressure test on the water line. • Continue underground electric and fiber optic duct bank installation. • Installation of oil interceptor. Site Construction Progress • Complete structural backfilling of interior foundations including haunches for CMU walls. • Continue under slab MEP installation. • Begin interior masonry wall installation at Area B and Area C storage areas while coordinating with MEP for in-wall rough-ins. • Prep & pour slab on grade in Area B and the depressed slab at the Training/EOC room. Building Construction Progress

• Prep and pour slab on grade in Area A. • Begin receiving structural steel deliveries. • Begin erection of structural steel columns.

y

Complete storm structure installation.

Slab on grade preparation in Area A

June 2021

New Central Emergency Services Facility

Projected Progress for July 2021

• Have all Primes sign off on coordination drawings. • Complete installation of the sediment basin and bermwork at southwest corner of the basin. • Cut in the new entrance at Black Rock Rd. for the apparatus bay. • Stabilize the southern half of the site. • Continue interior masonry wall installation and in-wall electrical rough-ins. • Complete under slab MEP installation including the interior section of the radiant heat system. • Complete erection and detailing of structural steel. • Complete placement of pre-cast concrete panels forming the mezzanine floor. • Begin slab on grade preparation in Area C.

Door frame and interior CMU installation.

Placement of slab on grade in Area A.

y

Erection of structural steel columns.

Delivery of generator and under slab rough-in of electrical duct bank from transformer vault.

June 2021

Building Layout

Aerial view of building foundations and material laydown area (May 2021).

Site Overview (May 2021).

June 2021

Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001

20

Overall Project Schedule Status

J

F M A M J

Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals

P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement

P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP C i i i P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping

P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion

Current Phase and Schedule Status

J F M A M J

P1.4 ‐ Establish temporary power, site lighting, and communications from existing utilities. P1.6 ‐ Install basin and perform site rough grading P1.8‐P1.11 ‐ Install MEP to building pad P1.13 ‐ Place building foundations P1.14 ‐ Complete under slab MEP piping and conduit

P1.15 ‐ Complete Slab on Grade P1.16 ‐ Slab on Grade Curing Time P1.17 ‐ Erect Structural Steel

Issues Resolved Coordinate new Day Room and Office 101 layout with Primes and GKO. Confirm installation details of the radient heat system allowing the MC to use manufacturer approved joints. Confirm new construction sequence and water pumping detail of the sediment basin proposed by Lobar, with Gilmore and Montgomery County Co Review the GC erection sequence of structural steel and how the pre‐cast concrete planks integrate into the building superstructure.

Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.

Contract Amount

$ $ $ $ $

7,462,000 1,123,000 1,212,400

922,197

10,719,597

Total Total Soft Costs: Current Remaining Project Contingency

Other Discussion

Report Submission Date: June 2021

Report Author: Michael DePodwin

021

2022

J

A S O N

D J

F M A M J

% Complete

Status Comments

Resubmittals nearing completion

60% 0% 0% 0% 0% 0% 95%

Slab on Grade and Structural Steel Ongoing

Storm and water line complete. Underground rough‐in underway

95%

0% 0% 0% 5% 0% 0%

Curb for new entrance off Black Rock Rd. ‐ 07/12/21

Phase 1 2021

Status Comments

J A S O N D J F M A M J

% Complete

100%

Complete

95% Baffle and stabilitzation to occur week of 07/12/21

90%

All utilities have been terminated building side save for gas.

100% Complete

50% Area B slab on grade complete 66% 50% Area A slab on grade ongoing. 15% Steel on site, erection ongoing.

MEP rough‐in continuing in apparatus bay and mechanical room

Issues in Progress

Continue to coordinate the FF&E process with GKO and the Township. GKO to confirm building efficiency through a COMCheck stemming from perimeter insulation question. Continue tracking the submittal process, notably fire protection shop drawings.

onservation District.

Continue to monitor Schedule, notably delivery of trench drains. Continue to monitor Erosion & Sedimentation Controls.

Paid to Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $

2,007,992

$ $ $ $ $

‐ ‐ ‐ ‐

$ $ $ $ $

209,365 47,807 94,098 37,920 389,190

$ $ $ $ $

189,198 47,807 92,910 64,622 394,537

129,598 196,856 253,244

2,587,691

1% Submittals

Requests for Information

0%

Approved Rejected Voided Overdue

3% 0%

16%

0%

Complete Outstanding Voided

83%

97%

Printed 7/9/2021

Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services

Board of Supervisors Bill Starling – Chair Laurie Higgins – Vice Chair

Helene Calci John Pearson Albert Vagnozzi

Construction Manager D’huy Engineering, Inc.

Project Architect Gko Architects, Llc

Civil Engineer Gilmore & Associates, Inc.

Contractors Lobar, Inc. General Construction

Tri-County Mechanical, Inc. Mechanical Construction

Electri-Tech, Inc. Electrical Construction

Vision Mechanical, Inc. Plumbing Construction