Montgomery County Pandemic Recovery Funds Grant Application Package
BUDGET REASONABLENESS - $108M The estimated total cost of the project is: Construction Cost: $93,303,700 Soft Cost: $15,698,500 (Design Fees, Permits, Etc.) Hazardous Materials $700K The project budget is updated monthly and has been escalated due to current market conditions. The budget is based upon the cost of similarly sized facilities & others recent schools bids. A detailed cost estimate accompanies this submission. Abatement: Demolition: $1.35M
SCHEDULE
A detailed project schedule accompanies this submission. The project is on schedule and in the final phase of design and permitting. The project has preliminary approvals from the school board, Horsham Township, and the Montgomery County Planning Commission. Construction is to occur between October 2022 and August 2025 for the building. Recreation fields will be complete in 2026.
PROJECT MONITORING
MEASURING IMPACT
The status of the project is monitored during bi-weekly meetings with the District team. This will continue during construction. The project’s construction manager will provide monthly schedule updates and monthly financial reports to track schedule, costs and issues. The same District teammonitored the recent elementary school projects both of which were delivered on time and under budget.
Requests from the community to use the dated facilities at the existing High School often exceed the available capacity. The additional space for community after school programs in the new building will minimize conflicts between programs and allow growth of existing and new community-led programs. Indoor and outdoor teaching , athletic and performance spaces support adaptable and resilient programs for student, faculty and community regardless of pandemic conditions.