Montgomery County Intermediate Unit 23

SOME RECENT DEI PROJECT EXPERIENCE LEADING TO GREAT RESULTS FOR OUR CLIENTS

Pre-Bid Construction Estimate and Actual Bid Amount Total

Final Construction Costs including Change Order Amount

Project Name, Description, & Reference

Number of Prime Contractors & Square Footage

Start / Completion Dates

School District

Project Address

Newtown Middle School New Construction

4

05/2016 - 05/2018 School Complete with Demo of Old School Complete 04/2019

Estimate $49,705,000 Actual $46,300,000

$46,600,000

Doug Taylor Dir. of Op. Services 215-944-1015 dougtaylor@crsd.org Stony Creek Elementary School Expansion & Renovation Wade Coleman Business Manager 215-619-8000 wcoleman@wsdweb.org

180,000 SF

Council Rock School District

116 Richboro Newtown Rd, Newtown, PA 18940

4

Estimate $16,103,000 Actual $15,504,000

08/2020 - 11/2022

$15,500,000

26,700 SF Expansion 16,000 SF Renovation

Wissahickon School District

1721 Yost Rd, Blue Bell, PA 19422

Upper Perkiomen Middle School New Construction

4

Estimate $49,900,000 Actual $45,898,000

07/2017 - 08/2019

$45,875,000

Doug Kenwood Director of Facilities 267-718-5449 dkenwood@upsd.org

204,580 SF

Upper Perkiomen School District

901 Montgomery Ave, Pennsburg, PA 18073

Nitschmann Middle School New Construction

4 Plus Environmental Abatement

03/2015 - 08/2017 School Complete 08/2017 Field Complete 08/2018

Estimate $47,000,000 Actual $46,334,000

$46,100,000

Mark Stein, PE Dir. Of Facilities 610-867-8635 mstein@basdschools.org

180,000 SF and Synthetic Turf Field

Bethlehem Area School District

1002 WUnion Blvd, Bethlehem, PA 18018