Work Ongoing

Work Completed

• Submittal processing • Steel wall angle bracing • Coordination for placement of roof curbs • Interior CMU non-bearing walls • Coordination with PPL for switch out of service with respect to new transformer location • Ongoing third-party inspections • Ongoing plumbing inspections • Ongoing electrical CMU wall rough-in • Ongoing MEP coordination of required wall openings in CMU walls • Interior door frame installations • Coordination and installation of roof drains • Coordination of pressure grouting sink hole area • Installation of feeder conduits towards new panels in Classroom addition • Coordination with switchgear change-out • Coordination with new transformer installation • Installation of above ceiling MEP work • Installation of Parapet wall steel plate and angle supports • Installation of underground plumbing to Nurses area, in old Stage room

• Installation of stone base for concrete slab in old Stage area • Roofing material delivery and coordination to commence

Parapet Plate Steel

Made with FlippingBook Ebook Creator