Lower Nazareth Elementary School
Report Submission Date:
01/31/21
Report Author: Lee Werkheiser
2021
2022
Status Comments
A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D
% Complete
100% Phase 1 site work has been completed
Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete. Above Ceiling HVAC ducts installed. Above ceiling MC cable and junction boxes installed.
100%
97%
9%
0%
Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced. Joist installation is planned.
50%
0%
0%
0%
0%
ng Phase 1 2021
Status Comments
M A M J J A S O N D
% Complete
Installation of door frames and interior CMU walls. 2 HR separation walls framed, Fire proofing completed on Door structural frame. Generator slab poured. Electrical panels installed Overhead MEP work commenced. Installation of protective barrier for demolition complete. Selective demolition of Stage and excavation. Prepared Building pad of addition. Completed Foundations and underslab MEP work. Erected structural steel. Poured Concrete slab. Framed stud wall at Cafeteria and sheetrocked.
97%
44%
Smaller sinkhole pressure grouting at West Elevation after snow melts Issues in Progress
o Date (with 10% retained)
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
1,820,874
$ $ $ $ $ $
‐ ‐ ‐ ‐ ‐ ‐
$ $ $ $ $ $
2,934 42,270 515,354 70,490 43,280 356,380
$ $ $ $ $ $
356,380 43,280 55,960 42,270
222,702 208,806 298,822
2,273
2,934
2,553,477
500,824