Lower Nazareth Elementary School
Report Submission Date:
12/01/20
Report Author: Lee Werkheiser
2021
2022
Status Comments
M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D
% Complete
100% Phase 1 site work has been completed
Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete.
100%
66%
0%
0%
Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced.
45%
0%
0%
0%
0%
ilding Phase 1 2020
Status Comments
F M A M J J A S O N D
% Complete
All underslab MEP work complete. CMU load bearing walls complete. Roof steel complete. Decking complete. Concrete slab complete. Installation of protective barrier for demolition complete. Selective demolition of Stage and excavation. Prepaired Building pad of addition. Completed Foundations and underslab MEP work. Erected structural steel. Poured Concrete slab. Framed stud wall at Cafeteria and sheetrocked.
97%
44%
smaller sinkhole pressure grouting at West Elevation Issues in Progress
Remaining Material Allowance
d to Date (with 10% retained)
Original Material Allowance
Executed Change Orders
1,430,514
$ $ $ $
‐ ‐ ‐ ‐
$ $ $ $
70,490 42,270 43,280 356,380
$ $ $ $
356,380 43,280 70,490 42,270
184,002 161,082 282,223