Lower Nazareth Elementary School - February & March Monthly Report

Work Completed - March

Work Completed - March

• Toilet roomwall framing in Classroom addition. • Interior CMU rubdown of walls in Classroom addition. • Installation of mechanical roof curbs. • Installation of built-up roof insulation and watertight at Classroom addition. • Interior CMU wall block prime and paint at Classroom addition. • Steel Wall angle bracing in Classroom addition. • Placement of mechanical roof curbs on Classroom addition. • Coordination of Pressure grouting sink hole area. • Installation of feeder conduits to new panels in Classroom addition. • Interior framing at each classroom entrance. • Framing of P-lam ceiling areas. • Installation of above ceiling circuits in Classroom addition. • Installation of tackboards and white boards in Classrooms of Classroom addition. • Installation of casework in Classroom addition. • Installation of concrete slab in old stage area and Admin addition. • Installation of ceiling grid in Classrooms of Classroom addition. • Installation of plumbing insulation, labeling and valve tagging in Classroom addition. • Topping out exterior perimeter CMU walls and steel plate installation on top of perimeter walls.

Coordination of Demolition in Work Room

Made with FlippingBook - Online catalogs